Energy Projects Near You

Mona offshore wind farm

Mona Offshore Wind Farm is a 1,500 MW offshore wind farm with 96 turbines in UK waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2025, not yet built; the record was last updated on 3 March 2026. Its REPD grid reference is 33 km from the nearest postcode on land (LL30 2XD, Conwy). As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010137).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,500 MWoffshore wind farm
approved, not builtstatus in REPD
3 March 2026record last updated
33 km from land (Conwy)REPD location

Consent timeline

DateStage
22 February 2024Application submitted
4 July 2025Development consent granted (Secretary of State)

Project details

Technology
offshore wind farm
Capacity
1,500 MW
Turbines
96
Turbine capacity
15.6 MW
Turbine height
324 m
Status (REPD)
approved, not built
Record last updated
3 March 2026
Operator or applicant
BP Oil UK Limited / ENBW UK Limited
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010137
Nearest postcode on land
LL30 2XD (Conwy), 32.8 km from the REPD grid reference
Time to decision
71 weeks
REPD reference
10918

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010137). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Llandudno (LL30)35.3
Llandudno Junction (LL31)38.4
Colwyn Bay (LL28)38.9
Colwyn Bay (LL29)39.3

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Awel y Mor Offshore Wind Farm775approved, not built19.0
Gwynt y Mor576operational24.3

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.6352, -3.8317).

Mona was approved faster than usual, but in the REPD extract for July 2026 it is not built. The application for a development consent order was submitted on 22 February 2024, and after examination by the Planning Inspectorate the Secretary of State for Energy Security and Net Zero granted consent on 4 July 2025: 71 weeks against a median of 84.4 for offshore wind. The Energy Secretary at the time was Ed Miliband, in post from 5 July 2024 to 20 July 2026 (GOV.UK). Similar cases are collected in the section Energy Secretary decisions. The data contains no construction timelines.

Neighbours on the north Wales coast

Morgan, from the same applicants, also 1,500 MW and 96 turbines, received its DCO on 29 August 2025. In January 2026 EnBW pulled out of both projects: Mona continues under JERA Nex bp, Morgan is halted. At 19.0 km, Awel y Mor with 775 MW is approved, and at 24.3 km Gwynt y Mor has been operational since 2015. Its 3.6 MW turbines are more than four times weaker than Mona's 15.6 MW machines, which stand up to 324 m tall. The nearest postcode districts: Llandudno and Colwyn Bay.