Energy Projects Near You

Bretton Hall Solar Farm (England) (14 MW)

Bretton Hall Solar Farm (England) is a 14 MW solar farm project in Flintshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 October 2023, not yet built; the record was last updated on 12 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWsolar farm
approved, not builtstatus in REPD
12 October 2023record last updated
Flintshirecouncil area

Planning timeline

DateStage
31 May 2022Application submitted
12 October 2023Planning permission granted
12 October 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
14 MW
Status (REPD)
approved, not built
Record last updated
12 October 2023
Operator or applicant
YnNi Newydd (New Energy Co-op)
Planning authority
Flintshire
Planning application reference
22/02042/FUL
Site area
23.8 ha
Address (REPD)
Bretton Hall Farm, Chester Road, Bretton, Chester,
Council area (by location)
Flintshire
Time to decision
71 weeks
REPD reference
7940

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsFlintshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused2 of 1312%
Onshore wind refused2 of 345%
Battery storage refused0 of 216%
Median time from submission to decision30.3 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bretton Hall Solar Farm (Wales)solar farm16approved, not built0.5
Wood Farm Solar Park (linked site)solar farm5refused on appeal3.7
Banks Farm Solar Park (linked site)solar farm5refused on appeal4.3
Huntington Water Treatment Workssolar farm7.2operational5.6
Portmanmoor Road Industrial Estate, Splott Battery Storage Unitsbattery storage10approved, not built8.1
Electricity Substation, Bellevue Lanebattery storage40approved, not built8.1
Mollingtonbattery storage240approved, not built8.5
Land West Of Vicarage Lanesolar farm5application submitted8.7
Shotwick Solar Farmsolar farm72.2operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1678, -2.9505).