Solar, wind and battery projects near Northwich (CW8)
19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CW8 (Cheshire West and Chester): 3 are waiting for a planning decision, 15 approved but not yet running. The largest live scheme is Wallerscote Limebeds (30 MW battery storage, approved on 21 July 2025, not yet built), 1.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CW8
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wallerscote Limebedsbattery storage | battery storage | 30 | approved, not builtupdated Aug 2025 | Sep 2023 | granted Jul 2025 | Aug 2025 | Cheshire West and Chester | 1.8 |
| Wallerscote Limebeds Solar Pv Parksolar farm | solar farm | 22 | approved, not builtupdated Aug 2025 | Sep 2023 | granted Jul 2025 | Aug 2025 | Cheshire West and Chester | 1.8 |
| Stublach Project Solar Farmsolar farm | solar farm | 2.2 | approved, not built may be out of dateupdated Jan 2021 | Nov 2020 | granted May 2021 | Jan 2021 | Cheshire West and Chester | 7.4 |
| Aston Grange, Aston Solar Panels & Battery Energy Storage Systemsolar farm | solar farm | 20 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Cheshire West and Chester | 7.5 |
| Aston Grange, Aston Solar Panels & Battery Energy Storage Systembattery storage | battery storage | 6 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Cheshire West and Chester | 7.5 |
| Aston Grange Farmwind farm | wind farm | 12 | refused on appealupdated Nov 2011 | Jun 2005 | refused Oct 2006 | Nov 2011 | Cheshire West and Chester | 7.5 |
| Schoeller Allibert Limited, Road One Solar Panels Systemrooftop solar | rooftop solar | 2.2 | approved, not built may be out of dateupdated Mar 2023 | May 2022 | granted Jan 2023 | Mar 2023 | Cheshire West and Chester | 7.9 |
| Woodford Lane West Solar Farm (Hebden Green)solar farm | solar farm | 19 | approved, not builtupdated Feb 2026 | Jul 2023 | granted Jul 2024 | Feb 2026 | Cheshire West and Chester | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| The County High School Leftwich, Granville Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Cheshire West and Chester | 4.1 |
| Specialist Technical Products, Smokehall Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Cheshire West and Chester | 6.4 |
| Morrison Supermarkets Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Cheshire West and Chester | 7.0 |
| Tiger Trailers, Winsford Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Cheshire West and Chester | 7.1 |
| Tiger Trailers, Road Onerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Cheshire West and Chester | 7.1 |
| Winsford Lifestyle Centrerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2021 | Sep 2021 | granted Oct 2021 | Dec 2021 | Cheshire West and Chester | 7.5 |
| Hosokawa Micron, Rivington Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Halton | 8.5 |
| Phoenix Medical Supplies, Rivington Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 | Halton | 8.6 |
| Kelsall Hill Equestrian Centre, Middlewich Roadrooftop solar | rooftop solar | 0.4 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Cheshire West and Chester | 9.0 |
| Lady Heyes Camping And Caravan Site, Kingsley Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Sep 2025 | Nov 2025 | Cheshire West and Chester | 9.2 |
| Spire Cheshire Hospital, Fir Tree Close Solar PV Systemsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Warrington | 9.4 |
Distance from the average position of the CW8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 4 | 0 | 0 | 63.6 |
| Rooftop solar | 11 | 1 | 10 | 0 | 0 | 5 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 2 | 1 | 1 | 0 | 0 | 36 |
MW in pipeline: pending, approved and under-construction capacity.
How Cheshire West and Chester decides solar, wind and battery applications
| Applications | Cheshire West and Chester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 54 | 10,236 |
| Refused | 6 (11%) | 19% |
| Solar refused | 3 of 40 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 2 of 12 | 16% |
| Median time from submission to decision | 10.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
All projects in Cheshire West and Chester
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CW8, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.