Woodford Lane West Solar Farm (Hebden Green) (19 MW)

Woodford Lane West Solar Farm (Hebden Green) is a 19 MW solar farm project in Cheshire West and Chester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 July 2024, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Cheshire West and Chestercouncil area

Planning timeline

DateStage
25 July 2023Application submitted
25 July 2024Planning permission granted

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Anglo Renewables
Planning authority
Cheshire West and Chester
Planning application reference
23/02370/FUL
Site area
25.0 ha
Address (REPD)
S/O Woodford Lane West, Hebden Green
Council area (by location)
Cheshire West and Chester
Time to decision
52 weeks
Contracts for Difference
AR7a
Name in REPD
Woodford Lane West - Solar Farm (Hebden Green)
REPD reference
14643

Who decides

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Moss Farm (North)solar farm6permission expired8.6
Leighton Hall Farmbattery storage20permission expired8.6
Land at Moss Farm (South)solar farm5permission expired8.7
Drury Lanesolar farm17approved, not built9.0
Wallerscote Limebedsbattery storage30approved, not built9.3
Wallerscote Limebeds Solar Pv Parksolar farm22approved, not built9.3
Bentley Motors Ltd 1rooftop solar5.1operational9.5
Dragons Lanebattery storage12approved, not built9.7
High Street Solar Farmsolar farm17.6approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1747, -2.5553).