Leighton Hall Farm (20 MW battery storage)

Leighton Hall Farm is a 20 MW battery storage project in Cheshire East, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 20 November 2020; the record was last updated on 27 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
permission expiredstatus in REPD
27 May 2020record last updated
Cheshire Eastcouncil area

Planning timeline

DateStage
27 September 2017Application submitted
12 January 2018Planning permission granted
20 November 2020Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
permission expired
Record last updated
27 May 2020
Operator or applicant
Energy Demand and Response
Planning authority
Cheshire East
Planning application reference
17/4941N
Address (REPD)
Leighton Hall Farm, Middlewich Road, Leighton, Crewe, Cheshire
Council area (by location)
Cheshire East
Time to decision
15 weeks
REPD reference
7032

Who decides

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bentley Motors Ltd 1rooftop solar5.1operational0.9
Land at Moss Farm (South)solar farm5permission expired2.7
Land at Moss Farm (North)solar farm6permission expired2.8
Drury Lanesolar farm17approved, not built3.4
Middlewich Road Solar Photovoltaics & Battery Storagesolar farm5approved, not built4.3
Dragons Lanebattery storage12approved, not built7.3
Former EON Power Station, Booth Lanebattery storage20approved, not built7.8
Land south of Wood Lane (Safeguard Bradwell)solar farm5operational8.4
Woodford Lane West Solar Farm (Hebden Green)solar farm19approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1113, -2.4808).