Renewable energy projects in Cheshire East

44 solar, wind or battery projects of 150 kW or more are located in Cheshire East (REPD, July 2026 extract): 2 pending, 29 approved but not running, 6 operational and 2 refused. The council refused 4 of 40 decided applications (10%; UK 19%), with a median 11 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44projects in the council area
2awaiting a decision
29approved, not running
10%of decisions refused

How Cheshire East decides

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Projects in Cheshire East

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Middlewich Road Solar Photovoltaics & Battery Storagebattery storagebattery storage25approved, not built may be out of dateupdated Mar 2022Aug 2021granted Mar 2022Mar 2022
Leighton Hall Farmbattery storagebattery storage20permission expiredupdated May 2020Sep 2017granted Jan 2018May 2020
Former EON Power Station, Booth Lanebattery storagebattery storage20approved, not builtupdated May 2025Oct 2024granted Apr 2025May 2025
Drury Lanesolar farmsolar farm17approved, not built may be out of dateupdated Feb 2021Jun 2020granted Feb 2021Feb 2021
Combermere Abbeysolar farmsolar farm14operationalupdated Sep 2015May 2014granted Dec 2014Sep 2015
Hurst Hallsolar farmsolar farm13.3refused on appealupdated Mar 2016Sep 2014refused Dec 2014Mar 2016
Hatherton Lodge Farm, Hunsterson Road Solar Farmsolar farmsolar farm12.5approved, not builtupdated Feb 2026Dec 2024granted Jun 2025Feb 2026
Dragons Lanebattery storagebattery storage12approved, not built may be out of dateupdated Jul 2022Jul 2022granted Dec 2022Jul 2022
Hatherton Lodgesolar farmsolar farm8.3permission expiredupdated Nov 2019Sep 2014granted Feb 2016Nov 2019
Land at Moss Farm (North)solar farmsolar farm6permission expiredupdated Sep 2020May 2015granted May 2016Sep 2020
Bentley Motors Ltd 1rooftop solarrooftop solar5.1operationalupdated Apr 2013Mar 2011granted Jun 2011Apr 2013
Land at Moss Farm (South)solar farmsolar farm5permission expiredupdated Sep 2020May 2015granted May 2016Sep 2020
Land south of Wood Lane (Safeguard Bradwell)solar farmsolar farm5operationalupdated May 2017Mar 2015granted Sep 2015May 2017
Royals Wood Farmsolar farmsolar farm5abandonedupdated Jan 2019Aug 2015—Jan 2019
Middlewich Road Solar Photovoltaics & Battery Storagesolar farmsolar farm5approved, not built may be out of dateupdated Mar 2021Aug 2021granted Mar 2022Mar 2021
Land To The North Of Dairy House Farmsolar farmsolar farm3.4operationalupdated Jul 2016Jun 2015granted Sep 2015Jul 2016
Bentley Motorsrooftop solarrooftop solar2.9operationalupdated Jan 2019Aug 2016granted Nov 2016Jan 2019
Barclays Bank Plc, Radbroke Solar Carportsolar farmsolar farm2.5under constructionupdated Jan 2024Feb 2022granted Oct 2022Jan 2024
Bentley Motors Limited, Pyms Lanerooftop solarrooftop solar1.1approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
London Road, Holmes Chapel Photovoltaic Panelsrooftop solarrooftop solar1under constructionupdated Apr 2021Feb 2021granted Jul 2021Apr 2021
Bentley Motors Limited, Sunnybank Roadrooftop solarrooftop solar0.7approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023
Bridgemere Garden Centre,London Roadrooftop solarrooftop solar0.7approved, not builtupdated Jan 2023Aug 2022granted Sep 2022Jan 2023
Bentley Motors, Pyms Lanerooftop solarrooftop solar0.6approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025
Bentley Motors, Sunnybank Road Solar Photovoltaics Panelsrooftop solarrooftop solar0.5approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025
The Kings School, Alderley Roadrooftop solarrooftop solar0.5approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022
Building L1, Bentley Motors Limited, Pyms Lanerooftop solarrooftop solar0.5approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022
Pyms Lanerooftop solarrooftop solar0.5approved, not builtupdated Apr 2022Apr 2022granted May 2022Apr 2022
Eagle Bridge Health and Wellbeing Centre, Dunwoody Wayrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024
Alderley Park, Congleton Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Jul 2023granted Nov 2023Jan 2024
Arclid Sand Quarryrooftop solarrooftop solar0.4operationalupdated Jun 2026Aug 2025granted Oct 2025Jun 2026
Sunnybank Road Solar Photovoltaics Panelrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted May 2022May 2022
Fence House, Fence Avenuerooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Sep 2023granted Oct 2023Nov 2023
Building B2, Bentley Motors Limited, Pyms Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2022Apr 2022granted May 2022May 2022
The Kings School, Alderley Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022
Pets At Home, Epsom Avenuerooftop solarrooftop solar0.2application submittedupdated Mar 2026Feb 2026—Mar 2026
Reynolds Farm, Reynolds Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Mar 2025May 2025
Ergo Park, Pochin Wayrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025
Smeaton Wood Farm, Pinsley Green Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Jan 2025granted Feb 2025May 2025
Building A6, Bentley Motors Limited, Pyms Lane - Roof mounted solar photovoltaicsrooftop solarrooftop solar0.2approved, not builtupdated May 2022Apr 2022granted May 2022May 2022
The Food Warehouse, Grand Junction Wayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Jul 2025granted Sep 2025Dec 2025
New Alderley House, Hope Driverooftop solarrooftop solar0.1refusedupdated Nov 2023Sep 2023refused Oct 2023Nov 2023
Church House Farm, Warmingham Roadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Aug 2024granted Nov 2024Jan 2025
Yew Tree Farm, Hall Lanerooftop solarrooftop solar0.1approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025
Crewe Hall Hotel, Weston Roadrooftop solarrooftop solar—application submittedupdated Nov 2025Oct 2025—Nov 2025

Postcode districts in Cheshire East

DistrictProjects within 10 kmPendingApprovedOperational
CW1311215
CW2281194
CW4150132
CW5281174
CW10350284
CW11291214
CW123021
SK9363271
SK107150
SK115040
SK12314242
WA1611080

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Cheshire East by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.