Solar, wind and battery projects near Crewe (CW4)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CW4 (Cheshire East): 13 approved but not yet running, 2 operational. The largest live scheme is Former EON Power Station, Booth Lane (20 MW battery storage, approved on 11 April 2025, not yet built), 5.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CW4
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land south of Wood Lane (Safeguard Bradwell)solar farm | solar farm | 5 | operationalupdated May 2017 | Mar 2015 | granted Sep 2015 | May 2017 | Cheshire East | 5.8 |
| Former EON Power Station, Booth Lanebattery storage | battery storage | 20 | approved, not builtupdated May 2025 | Oct 2024 | granted Apr 2025 | May 2025 | Cheshire East | 5.9 |
| Dragons Lanebattery storage | battery storage | 12 | approved, not built may be out of dateupdated Jul 2022 | Jul 2022 | granted Dec 2022 | Jul 2022 | Cheshire East | 6.4 |
| Barclays Bank Plc, Radbroke Solar Carportsolar farm | solar farm | 2.5 | under constructionupdated Jan 2024 | Feb 2022 | granted Oct 2022 | Jan 2024 | Cheshire East | 7.0 |
| Stublach Project Solar Farmsolar farm | solar farm | 2.2 | approved, not built may be out of dateupdated Jan 2021 | Nov 2020 | granted May 2021 | Jan 2021 | Cheshire West and Chester | 7.4 |
| Schoeller Allibert Limited, Road One Solar Panels Systemrooftop solar | rooftop solar | 2.2 | approved, not built may be out of dateupdated Mar 2023 | May 2022 | granted Jan 2023 | Mar 2023 | Cheshire West and Chester | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| London Road, Holmes Chapel Photovoltaic Panelsrooftop solar | rooftop solar | 1 | under constructionupdated Apr 2021 | Feb 2021 | granted Jul 2021 | Apr 2021 | Cheshire East | 1.4 |
| Ergo Park, Pochin Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | Cheshire East | 5.6 |
| Arclid Sand Quarryrooftop solar | rooftop solar | 0.4 | operationalupdated Jun 2026 | Aug 2025 | granted Oct 2025 | Jun 2026 | Cheshire East | 6.4 |
| Reynolds Farm, Reynolds Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Mar 2025 | May 2025 | Cheshire East | 7.1 |
| Fields Farm, Occleston Greenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Cheshire West and Chester | 7.9 |
| Church House Farm, Warmingham Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2025 | Aug 2024 | granted Nov 2024 | Jan 2025 | Cheshire East | 8.9 |
| Tiger Trailers, Road Onerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Cheshire West and Chester | 9.5 |
| Tiger Trailers, Winsford Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Cheshire West and Chester | 9.5 |
| Specialist Technical Products, Smokehall Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Cheshire West and Chester | 10.0 |
Distance from the average position of the CW4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 2 | 1 | 0 | 4.8 |
| Rooftop solar | 10 | 0 | 9 | 1 | 0 | 4.5 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 32 |
MW in pipeline: pending, approved and under-construction capacity.
How Cheshire East decides solar, wind and battery applications
| Applications | Cheshire East | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 4 (10%) | 19% |
| Solar refused | 4 of 36 | 12% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 11.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CW4, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.