Solar, wind and battery projects near Knutsford (WA16)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WA16 (Cheshire East): 8 approved but not yet running. The largest live scheme is Sunbank Lane (4.3 MW rooftop solar, approved on 17 April 2026, not yet built), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
8approved, not running
0operational

Projects within 10 km of WA16

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Barclays Bank Plc, Radbroke Solar Carportsolar farmsolar farm2.5under constructionupdated Jan 2024Feb 2022granted Oct 2022Jan 2024Cheshire East3.9
Sunbank Lanerooftop solarrooftop solar4.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Manchester7.9
Sunbank Lane Solar Panelsrooftop solarrooftop solar1.5approved, not built may be out of dateupdated Jun 2021May 2021granted Jul 2021Jun 2021Manchester8.1
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Thg Icon, Sunbank Lane, Unit 2rooftop solarrooftop solar0.8refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester8.1
Thg Studio, Sunbank Lanerooftop solarrooftop solar0.4refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester8.1
DHL Express Manchester, Sunbank Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Manchester8.1
Thg Icon, Sunbank Lane -Solar Arrayrooftop solarrooftop solar0.2refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester8.1
Dnata City North, Pinfold Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Manchester8.5
Sainsburysrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Trafford9.1
Tesco Extra Altrinchamrooftop solarrooftop solar0.5under constructionupdated Sep 2020Jul 2020granted Sep 2020Sep 2020Trafford9.3
Alderley Park, Congleton Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Jul 2023granted Nov 2023Jan 2024Cheshire East9.9

Distance from the average position of the WA16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101002.5
Rooftop solar1007037.7

MW in pipeline: pending, approved and under-construction capacity.

How Cheshire East decides solar, wind and battery applications

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Cheshire East

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WA16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.