Hatherton Lodge (8.3 MW solar farm)

Hatherton Lodge is an 8.3 MW solar farm project in Cheshire East, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 12 February 2019; the record was last updated on 29 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.3 MWsolar farm
permission expiredstatus in REPD
29 November 2019record last updated
Cheshire Eastcouncil area

Planning timeline

DateStage
11 September 2014Application submitted
5 March 2015Refused by the planning authority
4 June 2015Appeal lodged
12 February 2016Planning permission granted
12 February 2016Appeal allowed
12 February 2019Permission expired

Project details

Technology
solar farm
Capacity
8.3 MW
Status (REPD)
permission expired
Record last updated
29 November 2019
Operator or applicant
Green Switch Solutions - Liquidated
Planning authority
Cheshire East
Planning application reference
14/4296N
Appeal reference
APP/R0660/W/15/3033298
Site area
16.0 ha
Address (REPD)
Agricultural Land at Hatherton Lodge Farm, Hunterson Road, Hatherton, Nantwich
Council area (by location)
Cheshire East
Time to decision
74 weeks
REPD reference
4834

Who decides

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hatherton Lodge Farm, Hunsterson Road Solar Farmsolar farm12.5approved, not built0.7
Poplar Lane Wind Farmwind farm14refused on appeal7.3
Royals Wood Farmsolar farm5abandoned9.1
Combermere Abbeysolar farm14operational9.2
Bentley Motors Ltd 1rooftop solar5.1operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0173, -2.4622).