Energy Projects Near You

Solar, wind and battery projects near Macclesfield (SK10)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SK10 (Cheshire East): 1 is waiting for a planning decision, 5 approved but not yet running. The largest live scheme is Woodford Road (100 MW battery storage, approved on 30 May 2025, not yet built), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
1awaiting a decision
5approved, not running
0operational

Projects within 10 km of SK10

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodford Roadbattery storagebattery storage100approved, not builtupdated Jul 2025Dec 2024granted May 2025Jul 2025Stockport7.9
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
New Alderley House, Hope Driverooftop solarrooftop solar0.1refusedupdated Nov 2023Sep 2023refused Oct 2023Nov 2023Cheshire East1.5
Fence House, Fence Avenuerooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Sep 2023granted Oct 2023Nov 2023Cheshire East1.7
The Kings School, Alderley Roadrooftop solarrooftop solar0.5approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Cheshire East2.2
The Kings School, Alderley Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Cheshire East3.9
Alderley Park, Congleton Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Jul 2023granted Nov 2023Jan 2024Cheshire East6.6
Pets At Home, Epsom Avenuerooftop solarrooftop solar0.2application submittedupdated Mar 2026Feb 2026—Mar 2026Cheshire East10.0

Distance from the average position of the SK10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar614011.6
Battery storage10100100

MW in pipeline: pending, approved and under-construction capacity.

How Cheshire East decides solar, wind and battery applications

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Cheshire East

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.