Energy Projects Near You

Solar, wind and battery projects near Stockport (SK7)

39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SK7 (Stockport): 4 are waiting for a planning decision, 28 approved but not yet running, 3 operational. The largest live scheme is Woodford Road (100 MW battery storage, approved on 30 May 2025, not yet built), 2.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39projects within 10 km
4awaiting a decision
28approved, not running
3operational

Projects within 10 km of SK7

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Newby Road, Hazel Grovebattery storagebattery storage7.5approved, not built may be out of dateupdated May 2022Apr 2022granted Nov 2022May 2022Stockport1.5
Woodford Roadbattery storagebattery storage100approved, not builtupdated Jul 2025Dec 2024granted May 2025Jul 2025Stockport2.6
Torkington Road, Hazel Grovesolar farmsolar farm30application submittedupdated Aug 2025Jun 2025—Aug 2025Stockport4.3
Goyt Hall Farm, Goyt Valley Footpathbattery storagebattery storage40approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Stockport4.8
Bredbury Substationbattery storagebattery storage49.9under constructionupdated Sep 2021Sep 2021granted Dec 2021Sep 2021Stockport5.1
Welkin Road, Bredburybattery storagebattery storage20operationalupdated Jan 2026Dec 2020granted Jan 2021Jan 2026Stockport5.3
Welkin Mill, Welkin Roadbattery storagebattery storage49.9under constructionupdated Apr 2024Dec 2022granted Aug 2023Apr 2024Stockport5.5
Ashton Road, Bredburybattery storagebattery storage75approved, not builtupdated Aug 2025Jan 2025granted Jul 2025Aug 2025Stockport6.5
Tesco Store East Didsburyrooftop solarrooftop solar1approved, not builtupdated Feb 2021Nov 2019granted Jan 2020Feb 2021Manchester7.0
Tesco Burnage Storerooftop solarrooftop solar1approved, not builtupdated Jun 2020Nov 2019granted Jan 2020Jun 2020Manchester7.2
Denton Hall Farm Road, Dentonrooftop solarrooftop solar1.2operationalupdated Jan 2022Jan 2022granted Jul 2023Jan 2022Tameside9.0
Sunbank Lanerooftop solarrooftop solar4.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Manchester10.0
Smaller schemes under 1 MW, mostly rooftop solar (27)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bramhall High School, Seal Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Stockport0.6
The Adidas Centre, Hazel Groverooftop solarrooftop solar0.6approved, not builtupdated Feb 2023Sep 2022granted Feb 2023Feb 2023Stockport1.2
Sainsburys, London Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Stockport2.1
Adswood Roadbattery storagebattery storage—approved, not builtupdated Sep 2025Jan 2025granted Aug 2025Sep 2025Stockport3.0
Cheadle Hulme School, Claremont Roadrooftop solarrooftop solar0.3approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Stockport3.3
Hercules Office Park, Bird Hall Lane Solar Arraysrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Stockport3.7
Rrg Toyota, St Marys Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Stockport4.1
Bird Hall Lane, Cheadle Heathrooftop solarrooftop solar0.5approved, not builtupdated May 2026Dec 2025granted Mar 2026May 2026Stockport4.2
Life Leisure Grand Central, Grand Central Squarerooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Stockport4.4
Audi Stockport, Brinksway, Edgeleyrooftop solarrooftop solar0.3operationalupdated May 2022May 2022granted Oct 2023May 2022Stockport4.7
Pets At Home, Epsom Avenuerooftop solarrooftop solar0.2application submittedupdated Mar 2026Feb 2026—Mar 2026Cheshire East4.7
Decathlon, Georges Roadrooftop solarrooftop solar0.1approved, not builtupdated Apr 2024Mar 2024granted Apr 2024Apr 2024Stockport5.1
Heaton Norris Solar PV Panelrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Aug 2022May 2022Stockport5.1
Mercedes Benz, Heaton Merseyrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Stockport5.2
A G Parfett and Son, Didsbury Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Stockport5.2
Weinerberger House, Brooks Driverooftop solarrooftop solar0.1application submittedupdated Nov 2024Sep 2024—Nov 2024Stockport5.3
Styal Roadrooftop solarrooftop solar0.2application submittedMay 2026——Manchester6.3
Herrod Avenue, South Reddishbattery storagebattery storage—application withdrawnupdated Jun 2024Dec 2023—Jun 2024Stockport6.8
Scotscroft Towers Business Park, Wilmslow Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Manchester7.1
Gorton Education Village, Wembley Roadrooftop solarrooftop solar0.6approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Manchester9.4
Dnata City North, Pinfold Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Manchester9.6
New Mills Leisure Centre, Hyde Bank Roadrooftop solarrooftop solar0.1approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025High Peak9.6
Morrisons Superstore, Saxon Streetrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Tameside9.9
Thg Icon, Sunbank Lane, Unit 2rooftop solarrooftop solar0.8refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester9.9
Thg Studio, Sunbank Lanerooftop solarrooftop solar0.4refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester9.9
DHL Express Manchester, Sunbank Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Manchester9.9
Thg Icon, Sunbank Lane -Solar Arrayrooftop solarrooftop solar0.2refusedupdated Jul 2025May 2025refused Jul 2025Jul 2025Manchester9.9

Distance from the average position of the SK7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100030
Rooftop solar293212312.3
Battery storage90710322

MW in pipeline: pending, approved and under-construction capacity.

How Stockport decides solar, wind and battery applications

ApplicationsStockportUK
Decided applications (solar, wind, battery)2210,236
Refused1 (5%)19%
Solar refused1 of 1412%
Battery storage refused0 of 816%
Median time from submission to decision12.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Stockport

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SK7, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.