Energy Projects Near You

Hurst Hall (13.3 MW solar farm)

Hurst Hall is a 13.3 MW solar farm project in Cheshire East, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 12 February 2016; the record was last updated on 3 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.3 MWsolar farm
refused on appealstatus in REPD
3 March 2016record last updated
Cheshire Eastcouncil area

Planning timeline

DateStage
22 September 2014Application submitted
11 December 2014Refused by the planning authority
4 June 2015Appeal lodged
12 February 2016Appeal refused

Project details

Technology
solar farm
Capacity
13.3 MW
Status (REPD)
refused on appeal
Record last updated
3 March 2016
Operator or applicant
Green Switch Solutions
Planning authority
Cheshire East
Planning application reference
14/4380N
Appeal reference
APP/R0660/W/15/3011357
Site area
23.0 ha
Address (REPD)
Hurst Hall, Wrenbury Road, Marbury, Cheshire
Council area (by location)
Cheshire East
Time to decision
11 weeks
REPD reference
4835

Who decides

ApplicationsCheshire EastUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused4 of 3612%
Battery storage refused0 of 416%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Royals Wood Farmsolar farm5abandoned3.2
Combermere Abbeysolar farm14operational3.4
Chads Farm - Photovoltaic Arrays & Battery Storagesolar farm15application submitted3.8
Fields Farm (Agden)solar farm5operational5.9
Bubney Farmsolar farm40operational6.9
Hadley Solar Farmsolar farm6.6operational7.9
Twemlowssolar farm10operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0125, -2.642).