Bubney Farm (40 MW solar farm)

Bubney Farm is a 40 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2023; the record was last updated on 1 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
operationalstatus in REPD
1 February 2024record last updated
Wrexhamcouncil area

Planning timeline

DateStage
1 April 2021Application submitted
1 October 2021Planning permission granted
1 September 2022Construction started
28 March 2023Operational

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
operational
Record last updated
1 February 2024
Operator or applicant
AlphaReal
Planning authority
Shropshire
Planning application reference
21/01661/FUL
Site area
65.1 ha
Address (REPD)
Bubney Farm, Grindley Brook, Whitchurch
Council area (by location)
Wrexham
Time to decision
26 weeks
REPD reference
8146

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hadley Solar Farmsolar farm6.6operational1.7
Fields Farm (Agden)solar farm5operational2.2
Chads Farm - Photovoltaic Arrays & Battery Storagesolar farm15application submitted4.9
Hurst Hallsolar farm13.3refused on appeal6.9
Twemlowssolar farm10operational7.0
Combermere Abbeysolar farm14operational9.1
Royals Wood Farmsolar farm5abandoned9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.976, -2.726).