Energy Projects Near You

Solar, wind and battery projects near Malpas (SY14)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY14 (Cheshire West and Chester): 4 are waiting for a planning decision, 1 approved but not yet running, 4 operational. The largest live scheme is Chads Farm - Photovoltaic Arrays & Battery Storage (522 MW battery storage, application submitted on 21 February 2022, no decision recorded; REPD status may be out of date), 5.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
4awaiting a decision
1approved, not running
4operational

Projects within 10 km of SY14

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fields Farm (Agden)solar farmsolar farm5operationalupdated May 2017Jul 2015granted Feb 2016May 2017Cheshire West and Chester4.9
Chads Farm - Photovoltaic Arrays & Battery Storagebattery storagebattery storage522application submitted may be out of dateupdated Mar 2022Feb 2022—Mar 2022Cheshire West and Chester5.0
Chads Farm - Photovoltaic Arrays & Battery Storagesolar farmsolar farm15application submitted may be out of dateupdated Mar 2022Feb 2022—Mar 2022Cheshire West and Chester5.0
Bubney Farmsolar farmsolar farm40operationalupdated Feb 2024Apr 2021granted Oct 2021Feb 2024Wrexham6.8
Hadley Solar Farmsolar farmsolar farm6.6operationalupdated Dec 2015Jul 2014granted Oct 2014Dec 2015Shropshire8.4
Hurst Hallsolar farmsolar farm13.3refused on appealupdated Mar 2016Sep 2014refused Dec 2014Mar 2016Cheshire East8.7
Belton Farm, Beltonsolar farmsolar farm2.2under constructionupdated May 2025Nov 2023granted Apr 2024May 2025Shropshire9.0
Land south of Francis Landsolar farmsolar farm10permission expiredupdated Sep 2020May 2015granted Sep 2016Sep 2020Wrexham10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Carden Park Golf Resort Solar Farm & Substationsolar farmsolar farm—application submittedupdated Sep 2025Jul 2025—Sep 2025Cheshire West and Chester5.4
Bubney Farmbattery storagebattery storage—operationalupdated Feb 2024Apr 2021granted Oct 2021Feb 2024Wrexham6.8
Superstore And Premises, London Roadrooftop solarrooftop solar0.4application submittedupdated Aug 2024Aug 2024—Aug 2024Shropshire8.5

Distance from the average position of the SY14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8213117.2
Rooftop solar110000.4
Battery storage21010522

MW in pipeline: pending, approved and under-construction capacity.

How Cheshire West and Chester decides solar, wind and battery applications

ApplicationsCheshire West and ChesterUK
Decided applications (solar, wind, battery)5410,236
Refused6 (11%)19%
Solar refused3 of 4012%
Onshore wind refused1 of 245%
Battery storage refused2 of 1216%
Median time from submission to decision10.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Cheshire West and Chester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.