Energy Projects Near You

Twemlows (10 MW solar farm)

Twemlows is a 10 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 November 2015; the record was last updated on 1 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
1 February 2016record last updated
Shropshirecouncil area

Planning timeline

DateStage
8 September 2014Application submitted
20 February 2015Planning permission granted
15 August 2015Construction started
15 November 2015Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
1 February 2016
Operator or applicant
Sunsave 27 (Twemlows)/ Vogt solar
Planning authority
Shropshire
Planning application reference
14/03957/FUL
Site area
23.0 ha
Address (REPD)
Land On Runway At Twemlows Hall, Higher Heath, Whitchurch, Shropshire
Council area (by location)
Shropshire
Time to decision
24 weeks
REPD reference
4861

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hadley Solar Farmsolar farm6.6operational6.0
Bubney Farmsolar farm40operational7.0
Combermere Abbeysolar farm14operational7.5
Royals Wood Farmsolar farm5abandoned8.0
Hurst Hallsolar farm13.3refused on appeal8.3
Fields Farm (Agden)solar farm5operational8.4
Chads Farm - Photovoltaic Arrays & Battery Storagesolar farm15application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9379, -2.6436).