Energy Projects Near You

Solar, wind and battery projects near Liverpool (L25)

54 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L25 (Liverpool): 6 are waiting for a planning decision, 40 approved but not yet running, 4 operational. The largest live scheme is Sutton Manor (57 MW battery storage, approved on 16 September 2022, not yet built; REPD status may be out of date), 9.5 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 24.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54projects within 10 km
6awaiting a decision
40approved, not running
4operational

Projects within 10 km of L25

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Jaguar Land Rover Jaguar Plant, North Roadrooftop solarrooftop solar9.3approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Knowsley3.7
Ford Halewood Transmissions Spekere, Boulevardsolar farmsolar farm1.3approved, not builtupdated Dec 2023Jul 2023granted Dec 2023Dec 2023Knowsley3.8
Liverpool John Lennon Airport Solar Farmsolar farmsolar farm3refusedupdated Jan 2022Dec 2021refused Jun 2022Jan 2022Liverpool5.2
Battery Energy Storage Systembattery storagebattery storage6approved, not builtupdated May 2025Nov 2024granted Apr 2025May 2025Liverpool5.6
Lister Drivebattery storagebattery storage49.9operationalupdated Jan 2023Feb 2020granted Mar 2021Jan 2023Liverpool6.2
Liverpool Energy Management Facilitybattery storagebattery storage49.9operationalupdated Mar 2022Feb 2020granted Nov 2020Mar 2022Liverpool6.2
Carnegie Road (Phase 2)battery storagebattery storage40permission expiredupdated Jun 2019Mar 2019granted Dec 2019Jun 2019Liverpool6.2
Land at Carnegie Roadbattery storagebattery storage20operationalupdated Jan 2019Nov 2016—Jan 2019Liverpool6.2
Ditton Road Solar Microgridsolar farmsolar farm4approved, not builtupdated Feb 2026Jun 2024granted Jan 2025Feb 2026Halton7.0
St Michaels Road, Ditton Roadbattery storagebattery storage14approved, not builtupdated Nov 2023Nov 2022granted Oct 2023Nov 2023Halton7.1
Hedco, Desoto Roadsolar farmsolar farm3.5approved, not builtupdated May 2026May 2022granted Jun 2024May 2026Halton8.3
Eastham Balacing Services Plantbattery storagebattery storage27application withdrawnupdated Nov 2018Oct 2017—Nov 2018Wirral8.9
Larkins Farm, Gellings Lane Solar Farmsolar farmsolar farm1.5refusedupdated Aug 2024Oct 2023refused Jul 2024Aug 2024Knowsley9.2
Jaguar Landrover Phoenix Building, Eric Foundation Roadrooftop solarrooftop solar1.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Cheshire West and Chester9.4
Sutton Manorbattery storagebattery storage57approved, not built may be out of dateupdated Jun 2022Jun 2022granted Sep 2022Jun 2022St. Helens9.5
Cheshire Power Stationbattery storagebattery storage45approved, not built may be out of dateupdated Dec 2021Nov 2021granted May 2023Dec 2021Cheshire West and Chester9.6
D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Liverpool9.7
Coopers Lane, Kirkbybattery storagebattery storage49.5approved, not builtupdated May 2024Jul 2023granted Apr 2024May 2024Knowsley9.9
Smaller schemes under 1 MW, mostly rooftop solar (36)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Leisure United Simpson - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Liverpool1.8
Self Storage Liverpool South, Goodlass Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Liverpool2.8
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Knowsley3.2
Halewood Leisure Centre, Baileys Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Knowsley3.2
Renaissance Way - Plot 7 Solar PV Arrayrooftop solarrooftop solar—approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Liverpool3.5
Jaguar Land Rover, North Road - Ground Mounted Solar Panelssolar farmsolar farm—approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Knowsley3.7
Speke Hall Avenuebattery storagebattery storage—approved, not builtupdated Mar 2025Dec 2023granted Feb 2025Mar 2025Liverpool4.1
Estuary Boulevardrooftop solarrooftop solar0.6approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Liverpool4.1
Garston Shore Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Aug 2022Jun 2022granted Sep 2022Aug 2022Liverpool4.5
Sainsburys Supermarket, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Liverpool4.6
The Big Yellow Self Storage, Mill Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2023Apr 2023granted May 2023May 2023Liverpool4.9
Leisure United Jericho Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Liverpool5.0
Alder Hey Hospital, East Prescot Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Jan 2026granted Mar 2026Jun 2026Liverpool5.0
Aigburth Parkrooftop solarrooftop solar—approved, not builtupdated Apr 2021Feb 2021granted May 2021Apr 2021Liverpool5.8
Stanley Meat Market, Prescot Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Jul 2024Sep 2024Liverpool5.8
Earlsfield Park, Arley Driverooftop solarrooftop solar0.1application submittedupdated Feb 2025Jan 2025—Feb 2025Knowsley6.0
Tesco Superstorerooftop solarrooftop solar—approved, not builtupdated Mar 2021Jan 2021granted Apr 2021Mar 2021Liverpool6.7
Whiston Hospital, Warrington Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Oct 2025granted Dec 2025Apr 2026Knowsley7.0
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelsrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool7.9
HMS Eaglet, Sefton Street Wind Turbine & Solar Panelswind turbinewind turbine—application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Liverpool7.9
Dixons Croxteth Academy, Carr Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Liverpool8.2
North Liverpool Academy, Heyworth Streetrooftop solarrooftop solar0.2application submittedupdated Aug 2025Jul 2025—Aug 2025Liverpool8.6
Biffa Waste Services, Dock Road South Battery Storage Unitsbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Wirral8.7
Peter Gilding And Company, Caddick Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2024Oct 2024granted Dec 2024Dec 2024Knowsley8.8
Adlib House, Kitling Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Knowsley9.1
Port Of Liverpool Building, Mann Islandrooftop solarrooftop solar—approved, not builtupdated Jan 2026Dec 2025granted Feb 2026Jan 2026Liverpool9.1
Sainsburys, Jennifer Avenuerooftop solarrooftop solar0.5approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Liverpool9.1
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025St. Helens9.2
Lea Green Business Park, Eurolinkrooftop solarrooftop solar0.6approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024St. Helens9.2
Penrhyn Court, Penrhyn Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Feb 2026May 2026Knowsley9.4
Beverston Engineering, Unit Brooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Knowsley9.4
Mercedes-Benz, Pall Mallrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Liverpool9.5
Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Liverpool9.6
Leiria Way Car Parkbattery storagebattery storage—operationalupdated Feb 2021Feb 2020granted May 2020Feb 2021Halton9.8
Mere Grange, Leasiderooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025St. Helens9.8
Rivendell Nurseriesrooftop solarrooftop solar0.2application submittedJun 2026——Halton9.9

Distance from the average position of the L25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm604028.8
Rooftop solar315260018.9
Wind turbine110000
Battery storage1601040172

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201824.5
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201829.2
North Hoyle60operationalupdated Aug 201739.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Liverpool decides solar, wind and battery applications

ApplicationsLiverpoolUK
Decided applications (solar, wind, battery)2610,236
Refused0 (0%)19%
Solar refused0 of 1812%
Battery storage refused0 of 816%
Median time from submission to decision7.8 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Liverpool

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L25, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.