Coopers Lane, Kirkby (49.5 MW battery storage)

Coopers Lane, Kirkby is a 49.5 MW battery storage project in Knowsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 April 2024, not yet built; the record was last updated on 31 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
approved, not builtstatus in REPD
31 May 2024record last updated
Knowsleycouncil area

Planning timeline

DateStage
27 July 2023Application submitted
30 April 2024Planning permission granted
30 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
approved, not built
Record last updated
31 May 2024
Operator or applicant
Pelagic Energy
Planning authority
Knowsley
Planning application reference
23/02008/FUL
Address (REPD)
Coopers Lane, Kirkby, Liverpool
Council area (by location)
Knowsley
Time to decision
40 weeks
Name in REPD
Coopers Lane, Kirkby - Battery Storage Facility
REPD reference
14670

Who decides

ApplicationsKnowsleyUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused4 of 1812%
Battery storage refused1 of 216%
Median time from submission to decision7.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Knowsley, Knowsley Borough.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cut Lanebattery storage57application submitted1.0
Charleywood Road, Knowsley Industrial Parkbattery storage49.9abandoned1.2
Perimeter Road, Kirkbybattery storage165application submitted1.6
Battery Energy Storage Systembattery storage6approved, not built7.4
Lister Drivebattery storage49.9operational7.4
Liverpool Energy Management Facilitybattery storage49.9operational7.4
Carnegie Road (Phase 2)battery storage40permission expired7.4
Land at Carnegie Roadbattery storage20operational7.4
Gerard Hall Solar Farmsolar farm17refused on appeal7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4679, -2.8504).