Gerard Hall Solar Farm (17 MW)

Gerard Hall Solar Farm is a 17 MW solar farm project in West Lancashire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 January 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWsolar farm
refused on appealstatus in REPD
5 February 2016record last updated
West Lancashirecouncil area

Planning timeline

DateStage
11 June 2014Application submitted
17 October 2014Refused by the planning authority
18 February 2015Appeal lodged
18 January 2016Appeal refused

Project details

Technology
solar farm
Capacity
17 MW
Status (REPD)
refused on appeal
Record last updated
5 February 2016
Operator or applicant
Hive Energy
Planning authority
West Lancashire
Planning application reference
2014/0601/FUL
Appeal reference
APP/P2365/W/15/3002667
Site area
37.0 ha
Address (REPD)
Land North West And South West Of Gerard Hall Prescot Road Aughton Ormskirk Lancashire L39 6TA
Council area (by location)
West Lancashire
Time to decision
18 weeks
REPD reference
1844

Who decides

ApplicationsWest LancashireUK
Decided applications (solar, wind, battery)2410,236
Refused6 (25%)19%
Solar refused5 of 1612%
Onshore wind refused1 of 345%
Battery storage refused0 of 516%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Back Lane Solar Farmsolar farm5appeal withdrawn2.7
Fromby Lane Solar Farmsolar farm5appeal withdrawn3.6
Lower Alt Wind Farmwind farm42refused5.6
Perimeter Road, Kirkbybattery storage165application submitted6.2
Charleywood Road, Knowsley Industrial Parkbattery storage49.9abandoned6.2
Avondale Nurseries, Spa Lanebattery storage320approved, not built7.0
Coopers Lane, Kirkbybattery storage49.5approved, not built7.4
Cut Lanebattery storage57application submitted7.8
Unit 5 XL Business Parkbattery storage49.9under construction7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.525, -2.9086).