Energy Projects Near You

Fromby Lane Solar Farm (5 MW)

Fromby Lane Solar Farm is a 5 MW solar farm project in West Lancashire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 26 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
appeal withdrawnstatus in REPD
26 March 2020record last updated
West Lancashirecouncil area

Planning timeline

DateStage
28 July 2015Application submitted
9 October 2015Refused by the planning authority
5 April 2016Appeal lodged
22 April 2016Appeal withdrawn

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
appeal withdrawn
Record last updated
26 March 2020
Operator or applicant
Fromby Lane Solar
Planning authority
West Lancashire
Planning application reference
2015/0760/FUL
Appeal reference
APP/P2365/W/16/3146746
Site area
10.9 ha
Address (REPD)
Land To The Rear Of Old Waggoners Cottage, Formby Lane, Aughton
Council area (by location)
West Lancashire
Time to decision
10 weeks
REPD reference
5927

Earlier applications for this site

ApplicationMWSubmittedOutcome
Fromby Lane Solar Farm 2015/0425/FUL529 April 2015withdrawn 9 July 2015

Who decides

ApplicationsWest LancashireUK
Decided applications (solar, wind, battery)2410,236
Refused6 (25%)19%
Solar refused5 of 1612%
Onshore wind refused1 of 345%
Battery storage refused0 of 516%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Back Lane Solar Farmsolar farm5appeal withdrawn1.2
Gerard Hall Solar Farmsolar farm17refused on appeal3.6
Lower Alt Wind Farmwind farm42refused4.2
Land at Tip Fieldsolar farm5under construction6.2
Jemmys Carrsolar farm5under construction6.3
Ringtail Airfieldsolar farm5application withdrawn6.5
North Moss Lane Solar Photovoltaic Farmsolar farm9approved, not built6.9
Avondale Nurseries, Spa Lanebattery storage320approved, not built7.4
Orrell Hillsolar farm20refused7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5529, -2.9377).