Energy Projects Near You

Solar, wind and battery projects near Liverpool (L22)

63 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of L22 (Sefton): 4 are waiting for a planning decision, 45 approved but not yet running, 6 operational. The largest live scheme is Hawthorne Road (20 MW battery storage, under construction), 3.4 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Burbo Bank (90 MW, operational), 10.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

63projects within 10 km
4awaiting a decision
45approved, not running
6operational

Projects within 10 km of L22

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Royal Seaforth Dock, New Jenkins Shedsrooftop solarrooftop solar2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.3
Royal Seaforth Dock Wind Farmwind farmwind farm3operationalupdated Feb 2003Oct 1995granted Aug 1997Feb 2003Sefton1.5
Hawthorne Roadbattery storagebattery storage20under constructionupdated Sep 2020Jan 2020granted Mar 2022Sep 2020Sefton3.4
Port of Liverpool windwind farmwind farm10operationalupdated Jun 2010Aug 2005granted Dec 2005Jun 2010Sefton3.4
Huskisson Dock Building, Huskisson Dockrooftop solarrooftop solar1.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Liverpool5.2
Orrell Hillsolar farmsolar farm20refusedupdated Jul 2015Aug 2014refused Jun 2015Jul 2015Sefton5.5
Lower Alt Wind Farmwind farmwind farm42refusedupdated Apr 2017Dec 2015refused Nov 2016Apr 2017West Lancashire6.6
Burbo Bank Energy Storagebattery storagebattery storage2operationalupdated Feb 2020Apr 2017—Feb 2020Wirral7.4
Britannia Housebattery storagebattery storage10permission expiredupdated Oct 2023Sep 2017granted Dec 2017Oct 2023Wirral7.8
Beaufort Roadbattery storagebattery storage20permission expiredupdated Apr 2020Sep 2016—Apr 2020Wirral8.4
D H L Exel Supply Chain Burton Foods, Portal Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Liverpool8.9
Land at Carnegie Roadbattery storagebattery storage20operationalupdated Jan 2019Nov 2016—Jan 2019Liverpool9.2
Lister Drivebattery storagebattery storage49.9operationalupdated Jan 2023Feb 2020granted Mar 2021Jan 2023Liverpool9.2
Liverpool Energy Management Facilitybattery storagebattery storage49.9operationalupdated Mar 2022Feb 2020granted Nov 2020Mar 2022Liverpool9.2
Carnegie Road (Phase 2)battery storagebattery storage40permission expiredupdated Jun 2019Mar 2019granted Dec 2019Jun 2019Liverpool9.2
Back Lane Solar Farmsolar farmsolar farm5appeal withdrawnupdated Aug 2018Jul 2015refused Oct 2015Aug 2018Sefton9.3
Gerard Hall Solar Farmsolar farmsolar farm17refused on appealupdated Feb 2016Jun 2014refused Oct 2014Feb 2016West Lancashire9.5
Battery Energy Storage Systembattery storagebattery storage6approved, not builtupdated May 2025Nov 2024granted Apr 2025May 2025Liverpool9.8
Smaller schemes under 1 MW, mostly rooftop solar (45)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
CWT North Building, Royal Seaforth Dockrooftop solarrooftop solar0.1approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.1
Rubies 3 Building, Royal Seaforth Dockrooftop solarrooftop solar—application submitted may be out of dateupdated Jan 2024Jan 2024—Jan 2024Sefton1.2
Royal Seaforth Dock, Seaforthrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.2
Briggs Marine, Langton Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton1.2
Maritime IT Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton1.2
Royal Seaforth Dock, CWT Stores Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton1.3
Maritime Stores, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton1.3
Rubies 1 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.3
Rubies 2 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.3
Merlin AFS, Royal Seaforth Dockrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton1.3
Cwt Maintenance Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton2.5
Litherland High School, Sterrix Lanerooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sefton3.0
Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.2
Multiuser 2 Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.2
Royal Seaforth Dock, New Jenkins Shedsrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.4
Multiuser 4 Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.4
Multiuser 1 Building, Regent Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Sefton3.4
Multiuser 5 Building, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton3.8
Peel Road Energy Centrebattery storagebattery storage—permission expiredupdated Apr 2020Sep 2017granted Jun 2018Apr 2020Sefton3.9
Temp Control Buildingrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Sefton4.2
Waste Care, Lower Bank Viewrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Liverpool4.7
Heysham Box, Leckwith Roadbattery storagebattery storage0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Sefton4.8
Heysham Box, Leckwith Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Sefton4.8
Bulk Powder Terminals, Regent Roadrooftop solarrooftop solar0.7approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Liverpool5.0
Steel Terminal, Royal Seaforth Dockrooftop solarrooftop solar—approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Liverpool5.1
SCS Lighting & Renewables, Aintreerooftop solarrooftop solar0.3application submitted may be out of dateupdated Jun 2022Jun 2022—Jun 2022Sefton5.2
Pawfect Retreat, Moor Farmrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Sefton5.2
Meadows Leisure Centre, Hall Lanerooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Sefton6.4
St Marys College, Wallasey Villagerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Wirral6.4
Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Liverpool6.7
Sainsburys, Jennifer Avenuerooftop solarrooftop solar0.5approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Liverpool6.8
Deyes Academy Redevelopmentrooftop solarrooftop solar0.6under constructionupdated Aug 2022Mar 2022granted Jun 2022Aug 2022Sefton7.0
North Liverpool Academy, Heyworth Streetrooftop solarrooftop solar0.2application submittedupdated Aug 2025Jul 2025—Aug 2025Liverpool7.1
Mercedes-Benz, Pall Mallrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022Liverpool7.4
Tesco, Bidston Link Road, Bidstonrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Wirral8.2
Tesco Pharmacy, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Feb 2026granted May 2026Jun 2026Wirral8.2
Valley Road, Bidstonrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Wirral8.3
Suttons Farm, Lord Sefton Wayrooftop solarrooftop solar0.5approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024West Lancashire8.4
Port Of Liverpool Building, Mann Islandrooftop solarrooftop solar—approved, not builtupdated Jan 2026Dec 2025granted Feb 2026Jan 2026Liverpool8.4
Dixons Croxteth Academy, Carr Lane Eastrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Liverpool8.7
Tipographic, Morpeth Wharfrooftop solarrooftop solar0.8approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Wirral8.7
Rowan View Hospital, Villas Roadrooftop solarrooftop solar—approved, not builtupdated May 2026Nov 2025granted Apr 2026May 2026Sefton9.0
Rowan View Hospital, Villas Roadbattery storagebattery storage—approved, not builtupdated May 2026Nov 2025granted Apr 2026May 2026Sefton9.0
Stanley Meat Market, Prescot Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Jul 2024Sep 2024Liverpool9.6
Formby High Schoolrooftop solarrooftop solar0.4approved, not builtupdated May 2022Apr 2022granted Jun 2022May 2022Sefton9.7

Distance from the average position of the L22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300020
Rooftop solar434390011.8
Wind farm300210
Battery storage14064026.6

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Burbo Bank90operationalupdated Feb 201810.5
Burbo Bank Extension (Burbo Bank 2)258operationalupdated May 201816.0
North Hoyle60operationalupdated Aug 201728.6
Gwynt y Mor576operationalupdated Aug 202039.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Sefton decides solar, wind and battery applications

ApplicationsSeftonUK
Decided applications (solar, wind, battery)4010,236
Refused4 (10%)19%
Solar refused3 of 3312%
Onshore wind refused0 of 245%
Battery storage refused1 of 516%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Sefton

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near L22, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.