Solar, wind and battery projects near Llanfairpwllgwyngyll (LL61)
12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL61 (Isle of Anglesey): 4 are waiting for a planning decision, 5 approved but not yet running, 1 operational. The largest live scheme is Tyddyn Forgan, Llanddeiniolen (100 MW battery storage, approved on 23 January 2026, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LL61
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Parciau Farm Solar Parksolar farm | solar farm | 13.9 | operationalupdated Sep 2015 | Jun 2014 | granted Sep 2014 | Sep 2015 | Gwynedd | 3.7 |
| Tyddyn Forgan, Llanddeiniolenbattery storage | battery storage | 100 | approved, not builtupdated Feb 2026 | Apr 2025 | granted Jan 2026 | Feb 2026 | Gwynedd | 6.5 |
| Seion, Pentirbattery storage | battery storage | 99.9 | refusedupdated Mar 2026 | Apr 2025 | refused Jan 2026 | Mar 2026 | Gwynedd | 6.5 |
| Pentir Substation, Pentirbattery storage | battery storage | 57 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 | Gwynedd | 7.1 |
| Braint Wind Farmwind farm | wind farm | 2.6 | refusedupdated Sep 2016 | Aug 2013 | refused Jul 2015 | Sep 2016 | Isle of Anglesey | 7.7 |
| Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagewind farm | wind farm | 24 | application submittedupdated Dec 2025 | Sep 2025 | — | Dec 2025 | Isle of Anglesey | 7.8 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| M-SParcsolar farm | solar farm | 0.9 | application submittedupdated Apr 2026 | Mar 2026 | — | Apr 2026 | Isle of Anglesey | 3.2 |
| M-SParcbattery storage | battery storage | 0.4 | application submittedupdated Apr 2026 | Mar 2026 | — | Apr 2026 | Isle of Anglesey | 3.2 |
| W O Jones Printers Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | Isle of Anglesey | 7.0 |
| Cyngor Sir Ynys Monrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Jan 2024 | Jan 2024 | Isle of Anglesey | 7.1 |
| Caernarfon Road Solar Panelsrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Feb 2021 | Nov 2020 | granted Apr 2021 | Feb 2021 | Gwynedd | 7.5 |
| Townland of Meenakeeran, Tullycar Road Wind Farm & Battery Storagebattery storage | battery storage | — | application submittedupdated Dec 2025 | Sep 2025 | — | Dec 2025 | Isle of Anglesey | 7.8 |
Distance from the average position of the LL61 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 1 | 0 | 1 | 0 | 0.9 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.9 |
| Wind farm | 2 | 1 | 0 | 0 | 1 | 24 |
| Battery storage | 6 | 2 | 3 | 0 | 1 | 158 |
MW in pipeline: pending, approved and under-construction capacity.
How Isle of Anglesey decides solar, wind and battery applications
| Applications | Isle of Anglesey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 0 of 5 | 12% |
| Onshore wind refused | 3 of 7 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Isle of Anglesey
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL61, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.