Energy Projects Near You

Solar, wind and battery projects near Caernarfon (LL54)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL54 (Gwynedd): 1 is waiting for a planning decision. The largest live scheme is Derwin Fawr Wind Turbines Replacement (0.8 MW wind farm, application submitted on 29 September 2025, no decision recorded), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
1awaiting a decision
0approved, not running
0operational

Projects within 10 km of LL54

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land on Park Farmsolar farmsolar farm2.4refusedupdated Nov 2015Jul 2015refused Nov 2015Nov 2015Gwynedd2.1
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Derwin Fawr Wind Turbines Replacementwind farmwind farm0.8application submittedupdated Nov 2025Sep 2025—Nov 2025Gwynedd7.6

Distance from the average position of the LL54 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100010
Wind farm110000.8

MW in pipeline: pending, approved and under-construction capacity.

How Gwynedd decides solar, wind and battery applications

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Gwynedd

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.