Bodelith Isaf Wind Turbines (5 MW)
Bodelith Isaf Wind Turbines is a 5 MW wind farm project in Gwynedd, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 October 2015; the record was last updated on 4 November 2015.
5 MWwind farm
refusedstatus in REPD
4 November 2015record last updated
Gwyneddcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 April 2014 | Application submitted |
| 19 October 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 4 November 2015
- Operator or applicant
- Pennant Walters
- Planning authority
- Gwynedd
- Planning application reference
- C14/0291/04/LL
- Turbines
- 2
- Address (REPD)
- Land near Bodelith Isaf, Llandderfel, Bala, Gwynedd
- Council area (by location)
- Gwynedd
- Time to decision
- 80 weeks
- REPD reference
- 4288
Who decides
| Applications | Gwynedd | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 6 (32%) | 19% |
| Solar refused | 3 of 13 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Gaerwen Wind Farm | wind farm | 59.4 | application submitted | 2.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9416, -3.4964).