Energy Projects Near You

Llwyndyrys Farm (5 MW solar farm)

Llwyndyrys Farm is a 5 MW solar farm project in Gwynedd, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 9 November 2020; the record was last updated on 18 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
18 March 2020record last updated
Gwyneddcouncil area

Planning timeline

DateStage
10 August 2015Application submitted
9 November 2015Planning permission granted
9 November 2020Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
18 March 2020
Operator or applicant
Luminous Energy
Planning authority
Gwynedd
Planning application reference
C15/0810/40/LL
Site area
11.6 ha
Address (REPD)
Llwyndyrys Farm, Y Ffor, Pwllheli
Council area (by location)
Gwynedd
Time to decision
13 weeks
REPD reference
5575

Who decides

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9356, -4.3997).