Energy Projects Near You

Solar, wind and battery projects near Pwllheli (LL53)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL53 (Gwynedd): 1 is waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Ty Du Uchaf, Pentreuchaf (4.8 MW solar farm, application submitted on 12 July 2024, no decision recorded; REPD status may be out of date), 6.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
1awaiting a decision
1approved, not running
1operational

Projects within 10 km of LL53

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land off Lon Pin, Llanbedrog Solar Farmsolar farmsolar farm5refusedupdated Nov 2025Dec 2023refused Oct 2025Nov 2025Gwynedd1.4
Tyddyn Cae (Nefyn)solar farmsolar farm4.9operationalupdated Dec 2015Sep 2014granted Feb 2015Dec 2015Gwynedd3.4
Ty Du Uchaf, Pentreuchafsolar farmsolar farm4.8application submitted may be out of dateupdated Sep 2024Jul 2024—Sep 2024Gwynedd6.3
Nanhoron Estatesolar farmsolar farm5abandonedupdated Oct 2019Nov 2015granted Nov 2016Oct 2019Gwynedd7.0
Llwyndyrys Farmsolar farmsolar farm5permission expiredupdated Mar 2020Aug 2015granted Nov 2015Mar 2020Gwynedd8.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Nanhoron Home Farm, Nanhoronrooftop solarrooftop solar0.2approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022Gwynedd5.4

Distance from the average position of the LL53 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm510114.8
Rooftop solar101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Gwynedd decides solar, wind and battery applications

ApplicationsGwyneddUK
Decided applications (solar, wind, battery)1910,236
Refused6 (32%)19%
Solar refused3 of 1312%
Onshore wind refused2 of 345%
Battery storage refused1 of 316%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Gwynedd

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL53, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.