Energy Projects Near You

Solar, wind and battery projects near Rhayader (LD6)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of LD6 (Powys): 1 operational. The largest scheme is Bryn titli Windfarm (9.9 MW wind farm, operational since 1 June 1994), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of LD6

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bryn titli Windfarmwind farmwind farm9.9operationalupdated Oct 2018Mar 1993granted Aug 1993Oct 2018Powys7.4

Distance from the average position of the LD6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.