Solar, wind and battery projects near Rhayader (LD6)
1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of LD6 (Powys): 1 operational. The largest scheme is Bryn titli Windfarm (9.9 MW wind farm, operational since 1 June 1994), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LD6
Projects of 1 MW and more (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bryn titli Windfarmwind farm | wind farm | 9.9 | operationalupdated Oct 2018 | Mar 1993 | granted Aug 1993 | Oct 2018 | Powys | 7.4 |
Distance from the average position of the LD6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Powys decides solar, wind and battery applications
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.