Energy Projects Near You

Solar, wind and battery projects near Llandrindod Wells (LD1)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LD1 (Powys): 1 is waiting for a planning decision, 2 approved but not yet running. The largest live scheme is Radnor Forest, Llandegley - Nant Mithil Energy Park (198 MW wind farm, application submitted on 21 October 2025, no decision recorded), 7.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
1awaiting a decision
2approved, not running
0operational

Projects within 10 km of LD1

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hendy Wind Farmwind farmwind farm14.4under constructionupdated Sep 2020Jul 2014granted Oct 2018Sep 2020Powys6.9
Radnor Forest, Llandegley - Nant Mithil Energy Parkwind farmwind farm198application submittedupdated Jan 2026Oct 2025—Jan 2026Powys7.1
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Llysdinam Hall, Charity Trustsolar farmsolar farm0.1approved, not builtupdated Jan 2025Jan 2024granted Oct 2024Jan 2025Powys7.7

Distance from the average position of the LD1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.1
Wind farm21100212

MW in pipeline: pending, approved and under-construction capacity.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.