Energy Projects Near You

Solar, wind and battery projects near Llangammarch Wells (LD4)

No solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of LD4 (Llangammarch Wells) in the Renewable Energy Planning Database (July 2026 extract). The nearest is Royal Welsh Showground, Llanelwedd (0.3 MW rooftop solar, approved, not built), 11.2 km away.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.2 kmto the nearest project
0projects within 10 km
0awaiting a decision
0approved, not running
0operational

The nearest recorded project is Royal Welsh Showground, Llanelwedd, 11.2 km from the centre of LD4. Household rooftop panels and schemes below about 150 kW are not in the database.

How Powys decides solar, wind and battery applications

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

All projects in Powys