Hendy Wind Farm (14.4 MW)

Hendy Wind Farm is a 14.4 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2020; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.4 MWwind farm
under constructionstatus in REPD
23 September 2020record last updated
Powyscouncil area

Planning timeline

DateStage
14 July 2014Application submitted
18 May 2017Refused by the planning authority
16 August 2017Appeal lodged
25 October 2018Planning permission granted
25 October 2018Appeal allowed
1 July 2020Construction started

Project details

Technology
wind farm
Capacity
14.4 MW
Status (REPD)
under construction
Record last updated
23 September 2020
Operator or applicant
Njord Energy Ltd
Planning authority
Powys
Planning application reference
P/2014/0672
Appeal reference
APP/T6850/A/17/3176128
Turbines
7
Address (REPD)
Hendy
Council area (by location)
Powys
Time to decision
223 weeks
REPD reference
4377

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Radnor Forest, Llandegley - Nant Mithil Energy Parkwind farm198application submitted2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2345, -3.2741).