Hendy Wind Farm (14.4 MW)
Hendy Wind Farm is a 14.4 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2020; the record was last updated on 23 September 2020.
14.4 MWwind farm
under constructionstatus in REPD
23 September 2020record last updated
Powyscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 July 2014 | Application submitted |
| 18 May 2017 | Refused by the planning authority |
| 16 August 2017 | Appeal lodged |
| 25 October 2018 | Planning permission granted |
| 25 October 2018 | Appeal allowed |
| 1 July 2020 | Construction started |
Project details
- Technology
- wind farm
- Capacity
- 14.4 MW
- Status (REPD)
- under construction
- Record last updated
- 23 September 2020
- Operator or applicant
- Njord Energy Ltd
- Planning authority
- Powys
- Planning application reference
- P/2014/0672
- Appeal reference
- APP/T6850/A/17/3176128
- Turbines
- 7
- Address (REPD)
- Hendy
- Council area (by location)
- Powys
- Time to decision
- 223 weeks
- REPD reference
- 4377
Who decides
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Radnor Forest, Llandegley - Nant Mithil Energy Park | wind farm | 198 | application submitted | 2.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2345, -3.2741).