Bryn titli Windfarm (9.9 MW)
Bryn titli Windfarm is a 9.9 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 1994; the record was last updated on 3 October 2018.
9.9 MWwind farm
operationalstatus in REPD
3 October 2018record last updated
Powyscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 March 1993 | Application submitted |
| 9 August 1993 | Planning permission granted |
| 1 June 1994 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 9.9 MW
- Status (REPD)
- operational
- Record last updated
- 3 October 2018
- Operator or applicant
- Innogy
- Planning authority
- Powys
- Planning application reference
- R42978D
- Turbines
- 22
- Address (REPD)
- Bryntitli Platuae, North of Rhayader Powys
- Council area (by location)
- Powys
- Time to decision
- 21 weeks
- REPD reference
- 3015
Who decides
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bryn Blaen Wind Farm | wind farm | 13.8 | operational | 6.1 |
| Hirddywel | wind farm | 27 | application submitted | 9.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3672, -3.5656).