Bryn Blaen Wind Farm (13.8 MW)

Bryn Blaen Wind Farm is a 13.8 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2019; the record was last updated on 15 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.8 MWwind farm
operationalstatus in REPD
15 February 2024record last updated
Powyscouncil area

Planning timeline

DateStage
4 December 2014Application submitted
26 November 2015Appeal lodged
23 August 2016Planning permission granted
23 August 2016Appeal allowed
15 June 2017Construction started
1 January 2019Operational

Project details

Technology
wind farm
Capacity
13.8 MW
Status (REPD)
operational
Record last updated
15 February 2024
Operator or applicant
Njord Energy
Planning authority
Powys
Planning application reference
P/2014/1102
Appeal reference
APP/T6850/A/15/3133966
Turbines
6
Turbine height
100 m
Address (REPD)
land north of the village of Llangurig in Powys
Council area (by location)
Powys
Time to decision
90 weeks
REPD reference
2873

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryn titli Windfarmwind farm9.9operational6.1
Bryn Duwind farm16.4operational7.7
Mynydd y Gwynt Wind Farmwind farm89.1refused on appeal8.3
Hirddywelwind farm27application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4196, -3.5943).