Mynydd y Gwynt Wind Farm (89.1 MW)

Mynydd y Gwynt Wind Farm is an 89.1 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 February 2018; the record was last updated on 25 June 2020. As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010020).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

89.1 MWwind farm
refused on appealstatus in REPD
25 June 2020record last updated
Powyscouncil area

Planning timeline

DateStage
31 July 2014Application submitted
23 November 2015Refused by the planning authority
4 October 2017Appeal lodged
22 February 2018Appeal refused

Project details

Technology
wind farm
Capacity
89.1 MW
Status (REPD)
refused on appeal
Record last updated
25 June 2020
Operator or applicant
Mynydd y Gwynt Ltd
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010020
Turbines
27
Address (REPD)
Mynydd y Gwynt, Lllangurig, Llanidloes, Powys
Council area (by location)
Powys
Time to decision
69 weeks
REPD reference
4402

Official project record at the Planning Inspectorate (EN010020)

Earlier applications for this site

ApplicationMWSubmittedOutcome
Mynydd y Gwynt Wind Farm89.124 April 2014withdrawn 22 May 2014

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010020). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryn Duwind farm16.4operational3.3
Cefn Croes Wind Farmwind farm58.5operational5.1
Lluest y Gwynt Wind Farmwind farm50.4application submitted6.6
Bryn Blaen Wind Farmwind farm13.8operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4438, -3.7103).