Lluest y Gwynt Wind Farm (50.4 MW)

Lluest y Gwynt Wind Farm is a 50.4 MW wind farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 30 October 2025, no decision recorded; the record was last updated on 5 June 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50.4 MWwind farm
application submittedstatus in REPD
5 June 2026record last updated
Ceredigioncouncil area

Planning timeline

DateStage
30 October 2025Application submitted

Project details

Technology
wind farm
Capacity
50.4 MW
Status (REPD)
application submitted
Record last updated
5 June 2026
Operator or applicant
Statkraft UK/Eco2
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3246727
Turbines
12
Turbine height
180 m
Address (REPD)
Close to the village of Ponterwyd, east of Aberystwyth, Ceredigion
Council area (by location)
Ceredigion
REPD reference
7864

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynydd y Gwynt Wind Farmwind farm89.1refused on appeal6.6
Cefn Croes Wind Farmwind farm58.5operational6.9
Bryn Duwind farm16.4operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4567, -3.806).