Energy Projects Near You

Renewable energy projects in Ceredigion

19 solar, wind or battery projects of 150 kW or more are located in Ceredigion (REPD, July 2026 extract): 1 pending, 5 approved but not running, 9 operational and 1 refused. The council refused 2 of 19 decided applications (11%; UK 19%), with a median 36 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects in the council area
1awaiting a decision
5approved, not running
11%of decisions refused

How Ceredigion decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Projects in Ceredigion

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cefn Croes Wind Farmwind farmwind farm58.5operationalupdated Apr 2009Jul 2000granted Dec 2001Apr 2009
Lluest y Gwynt Wind Farmwind farmwind farm50.4application submittedupdated Jun 2026Oct 2025—Jun 2026
Mynydd Gorddu Wind Farmwind farmwind farm10.2operationalupdated May 2006Jan 1991granted Sep 1991May 2006
Maesygarnsolar farmsolar farm10abandonedupdated Nov 2018Aug 2015granted Aug 2016Nov 2018
Llangwyryfonwind farmwind farm9.4operationalupdated Mar 2010Dec 2001granted Mar 2003Mar 2010
Llwyn Du Solar Farmsolar farmsolar farm8operationalupdated Jun 2015Jul 2013granted Jan 2014Jun 2015
Blaenporth Solar Farmsolar farmsolar farm7permission expiredupdated Nov 2019May 2014granted Sep 2014Nov 2019
Crugmore Farmsolar farmsolar farm6.4operationalupdated Jul 2017Oct 2013granted Feb 2014Jul 2017
Rhos Garn Whirlgarnwind farmwind farm6refused on appealupdated Aug 2016Feb 2015refused May 2015Aug 2016
Nanthenfoel Farmssolar farmsolar farm5operationalupdated Mar 2017Jul 2015granted Nov 2015Mar 2017
Pant Cefn Farmsolar farmsolar farm2.9permission expiredupdated Nov 2018Oct 2015granted Jul 2016Nov 2018
Fferm Penglais Solar Farmsolar farmsolar farm2.5operationalupdated Oct 2022May 2021granted Oct 2021Oct 2022
Rheidol Wind Farmwind farmwind farm2.4operationalupdated Dec 2003Aug 1991granted Aug 1996Dec 2003
Aberporth Solar Farmsolar farmsolar farm1.5operationalupdated Jun 2015Jun 2014granted Dec 2014Jun 2015
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cambrian Cross Country, Trefilanwind turbinewind turbine0.5approved, not builtupdated Nov 2025Nov 2024granted Aug 2025Nov 2025
Monachty Bach, Pennantrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Jun 2025granted Aug 2025Nov 2025
National Library Of Wales, Penglaissolar farmsolar farm0.4approved, not builtupdated Feb 2024Feb 2023granted Jan 2024Feb 2024
National Library Of Wales, Penglais Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Feb 2023granted Feb 2024Mar 2024
Rhodfa Padarn, Llanbadarn Fawrrooftop solarrooftop solar0.2approved, not builtupdated May 2022Mar 2022granted Sep 2022May 2022

Postcode districts in Ceredigion

DistrictProjects within 10 kmPendingApprovedOperational
SA436104
SA442000
SA452000
SA463020
SA474010
SA483011
SY235032
SY245032
SY251001

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Ceredigion by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.