Llwyn Du Solar Farm (8 MW)

Llwyn Du Solar Farm is an 8 MW solar farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 February 2015; the record was last updated on 16 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
16 June 2015record last updated
Ceredigioncouncil area

Planning timeline

DateStage
8 July 2013Application submitted
20 January 2014Planning permission granted
1 September 2014Construction started
26 February 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
16 June 2015
Operator or applicant
Next Energy Solar Fund
Planning authority
Ceredigion
Planning application reference
A130555
Site area
16.8 ha
Address (REPD)
Llwyn Ddu, Blaenporth, Cardigan
Council area (by location)
Ceredigion
Time to decision
28 weeks
REPD reference
1827

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blaenporth Solar Farmsolar farm7permission expired0.9
Crugmore Farmsolar farm6.4operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1084, -4.5236).