Energy Projects Near You

Crugmore Farm (6.4 MW solar farm)

Crugmore Farm is a 6.4 MW solar farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2015; the record was last updated on 3 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWsolar farm
operationalstatus in REPD
3 July 2017record last updated
Ceredigioncouncil area

Planning timeline

DateStage
25 October 2013Application submitted
24 February 2014Planning permission granted
1 January 2015Construction started
25 March 2015Operational

Project details

Technology
solar farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
3 July 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Ceredigion
Planning application reference
A130807
Address (REPD)
Crugmore Farm, Penparc, Cardigan
Council area (by location)
Ceredigion
Time to decision
17 weeks
REPD reference
5233

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blaenporth Solar Farmsolar farm7permission expired6.0
Llwyn Du Solar Farmsolar farm8operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0918, -4.6206).