Energy Projects Near You

Solar, wind and battery projects near Boncath (SA37)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA37 (Pembrokeshire): 2 are waiting for a planning decision, 2 approved but not yet running, 2 operational. The largest live scheme is Rhos-Hill, Cilgerran (0.6 MW wind turbine, application submitted on 25 August 2023, no decision recorded; REPD status may be out of date), 3.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
2awaiting a decision
2approved, not running
2operational

Projects within 10 km of SA37

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rhosygilwen Solar Farmsolar farmsolar farm1operationalupdated Aug 2011Nov 2010granted Jan 2011Aug 2011Pembrokeshire2.9
Crugmore Farmsolar farmsolar farm6.4operationalupdated Jul 2017Oct 2013granted Feb 2014Jul 2017Ceredigion8.6
Blaenffos Wind Turbineswind farmwind farm1refused on appealupdated Aug 2018Jul 2014refused Jun 2015Aug 2018Carmarthenshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rhos-Hill, Cilgerranwind turbinewind turbine0.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Pembrokeshire3.0
Bro Preseli Solar Panels & Battery Storagerooftop solarrooftop solar—application withdrawnupdated Oct 2024Jun 2023—Oct 2024Pembrokeshire6.0
Cwm Arian Community Solar Parksolar farmsolar farm0.5approved, not builtupdated May 2022Apr 2022granted Oct 2022May 2022Carmarthenshire8.5
Sarnau Farm, Trelechwind turbinewind turbine0.2approved, not builtupdated Jan 2026Jun 2025granted Nov 2025Jan 2026Carmarthenshire9.1
Blaenpant, Blaenwaunwind turbinewind turbine0.2application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023Carmarthenshire9.9

Distance from the average position of the SA37 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm301200.5
Rooftop solar100000
Wind farm100010
Wind turbine321001.1

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA37, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.