Energy Projects Near You

Solar, wind and battery projects near Llanfyrnach (SA35)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA35 (Pembrokeshire): 2 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Rhos-Hill, Cilgerran (0.6 MW wind turbine, application submitted on 25 August 2023, no decision recorded; REPD status may be out of date), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
2awaiting a decision
3approved, not running
3operational

Projects within 10 km of SA35

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dyffryn Brodyn Wind Farmwind farmwind farm5.5operationalupdated Jun 2010—granted Jan 1994Jun 2010Carmarthenshire6.8
Blaen Bowi Solar parksolar farmsolar farm8abandonedupdated May 2018Sep 2013granted May 2014May 2018Carmarthenshire8.0
Blaen Bowisolarsolar5.7permission expiredupdated Jul 2018Jan 2012granted Feb 2012Jul 2018Carmarthenshire8.0
Blaen Bowi Wind Farm (Extension)wind farmwind farm9.1refused on appealupdated Sep 2011Apr 2005refused Sep 2007Sep 2011Carmarthenshire8.5
Blaen Bowi Wind Farmwind farmwind farm3.9operationalupdated Aug 2004Jun 2000granted Jan 2001Aug 2004Carmarthenshire8.5
Rhosygilwen Solar Farmsolar farmsolar farm1operationalupdated Aug 2011Nov 2010granted Jan 2011Aug 2011Pembrokeshire8.7
Blaenffos Wind Turbineswind farmwind farm1refused on appealupdated Aug 2018Jul 2014refused Jun 2015Aug 2018Carmarthenshire8.7
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cwm Arian Community Solar Parksolar farmsolar farm0.5approved, not builtupdated May 2022Apr 2022granted Oct 2022May 2022Carmarthenshire3.5
Sarnau Farm, Trelechwind turbinewind turbine0.2approved, not builtupdated Jan 2026Jun 2025granted Nov 2025Jan 2026Carmarthenshire4.5
Blaenpant, Blaenwaunwind turbinewind turbine0.2application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023Carmarthenshire4.6
Bro Preseli Solar Panels & Battery Storagerooftop solarrooftop solar—application withdrawnupdated Oct 2024Jun 2023—Oct 2024Pembrokeshire6.4
Rhos-Hill, Cilgerranwind turbinewind turbine0.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Pembrokeshire8.7
Bwlchgwnt Solar Parksolar farmsolar farm0.6approved, not builtupdated Apr 2022Mar 2022granted Jul 2022Apr 2022Carmarthenshire9.6

Distance from the average position of the SA35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm402101.1
Rooftop solar100000
Solar100000
Wind farm400220
Wind turbine321001.1

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA35, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.