Energy Projects Near You

Solar, wind and battery projects near Glogue (SA36)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA36 (Pembrokeshire): 2 are waiting for a planning decision, 2 approved but not yet running, 2 operational. The largest live scheme is Rhos-Hill, Cilgerran (0.6 MW wind turbine, application submitted on 25 August 2023, no decision recorded; REPD status may be out of date), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
2awaiting a decision
2approved, not running
2operational

Projects within 10 km of SA36

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dyffryn Brodyn Wind Farmwind farmwind farm5.5operationalupdated Jun 2010—granted Jan 1994Jun 2010Carmarthenshire5.3
Rhosygilwen Solar Farmsolar farmsolar farm1operationalupdated Aug 2011Nov 2010granted Jan 2011Aug 2011Pembrokeshire8.7
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cwm Arian Community Solar Parksolar farmsolar farm0.5approved, not builtupdated May 2022Apr 2022granted Oct 2022May 2022Carmarthenshire2.8
Bro Preseli Solar Panels & Battery Storagerooftop solarrooftop solar—application withdrawnupdated Oct 2024Jun 2023—Oct 2024Pembrokeshire3.3
Blaenpant, Blaenwaunwind turbinewind turbine0.2application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023Carmarthenshire4.3
Sarnau Farm, Trelechwind turbinewind turbine0.2approved, not builtupdated Jan 2026Jun 2025granted Nov 2025Jan 2026Carmarthenshire8.1
Rhos-Hill, Cilgerranwind turbinewind turbine0.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Pembrokeshire8.7

Distance from the average position of the SA36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.5
Rooftop solar100000
Wind farm100100
Wind turbine321001.1

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SA36, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.