Energy Projects Near You

Solar, wind and battery projects near Clynderwen (SA66)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA66 (Pembrokeshire): 2 operational. The largest scheme is Caeremlyn Solar Farm (18 MW solar farm, operational since 31 March 2014), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
2operational

Projects within 10 km of SA66

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ambleston Solar Panelssolar farmsolar farm6operationalupdated Jan 2014Jun 2011granted Aug 2011Jan 2014Pembrokeshire8.5
Caeremlyn Solar Farmsolar farmsolar farm18operationalupdated Sep 2015May 2012granted Jan 2013Sep 2015Carmarthenshire9.9

Distance from the average position of the SA66 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200200

MW in pipeline: pending, approved and under-construction capacity.

How Pembrokeshire decides solar, wind and battery applications

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in Pembrokeshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.