Ambleston Solar Panels (6 MW)

Ambleston Solar Panels is a 6 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 January 2012; the record was last updated on 29 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
29 January 2014record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
16 June 2011Application submitted
11 August 2011Planning permission granted
24 October 2011Construction started
25 January 2012Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
29 January 2014
Operator or applicant
Arqiva Ltd
Planning authority
Pembrokeshire
Planning application reference
11/0104/PA
Site area
0.5 ha
Address (REPD)
Television Transmitter Centre, Ambleston, Haverfordwest, Dyfed, SA61
Council area (by location)
Pembrokeshire
Time to decision
8 weeks
Name in REPD
AMBLESTON SOLAR PANELS
REPD reference
1623

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cilciffeth 'B' Wind Farmwind farm7.8refused6.6
Cilciffeth 'A' Wind Farmwind farm7.8refused6.7
Trenewydd Wind Farmwind farm6.3refused6.7
Rudbaxton Solar Parksolar farm10.8operational8.0
Crundale / Fenton Home Farm (extension)solar farm5.9operational9.4
Fenton Home Farmsolar farm31.3operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8992, -4.8665).