Energy Projects Near You

Crundale / Fenton Home Farm (extension) (5.9 MW solar farm)

Crundale / Fenton Home Farm (extension) is a 5.9 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 20 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.9 MWsolar farm
operationalstatus in REPD
20 April 2015record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
3 September 2014Application submitted
12 November 2014Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
5.9 MW
Status (REPD)
operational
Record last updated
20 April 2015
Operator or applicant
Vogt Solar
Planning authority
Pembrokeshire
Planning application reference
14/0511/PA
Site area
11.2 ha
Address (REPD)
Fenton Home Farm, Crundale, Haverfordwest
Council area (by location)
Pembrokeshire
Time to decision
10 weeks
REPD reference
4830

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fenton Home Farmsolar farm31.3operational0.8
Shoals Hook Farmsolar farm12.1operational1.5
Rudbaxton Solar Parksolar farm10.8operational3.4
Cuckoo Grove Farmsolar farm6.1operational5.6
North Tenementsolar farm5operational6.6
Popehill Farmsolar farm5operational6.9
White House Farmsolar farm30application submitted7.1
Ambleston Solar Panelssolar farm6operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8236, -4.9284).