Cuckoo Grove Farm (6.1 MW solar farm)

Cuckoo Grove Farm is a 6.1 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.1 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
9 November 2012Application submitted
25 April 2013Planning permission granted
1 January 2015Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
6.1 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Pembrokeshire
Planning application reference
12/0744/PA
Address (REPD)
Land to the North of Cuckoo Grove Farm, Cuckoo Lane, Haverfordwest, SA61 2UY
Council area (by location)
Pembrokeshire
Time to decision
24 weeks
REPD reference
2376

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Tenementsolar farm5operational3.9
Popehill Farmsolar farm5operational4.2
Shoals Hook Farmsolar farm12.1operational4.5
Crundale / Fenton Home Farm (extension)solar farm5.9operational5.6
White House Farmsolar farm30application submitted5.8
Rudbaxton Solar Parksolar farm10.8operational5.9
Fenton Home Farmsolar farm31.3operational6.2
Tiers Cross Solar Farmsolar farm24operational7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8099, -5.0074).