Tiers Cross Solar Farm (24 MW)

Tiers Cross Solar Farm is a 24 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 October 2014; the record was last updated on 3 February 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
operationalstatus in REPD
3 February 2015record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
24 May 2013Application submitted
14 October 2013Planning permission granted
19 December 2013Construction started
25 October 2014Operational

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
3 February 2015
Operator or applicant
Good Energy Generation
Planning authority
Pembrokeshire
Planning application reference
13/0214/PA
Address (REPD)
Rose Cottage Farm; Woodson Farm; Tierson Farm, Tiers Cross, Milford Haven, Dyfed
Council area (by location)
Pembrokeshire
Time to decision
20 weeks
REPD reference
2074

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Liddeston Ridge Solar Park (Milford Haven)solar farm5operational3.4
Popehill Farmsolar farm5operational4.6
North Tenementsolar farm5operational4.8
White House Farmsolar farm30application submitted5.4
Dragon Energy Park Wind Farmwind farm14.4under construction5.5
Dragon Long Meadow Solar farmsolar farm9.9operational5.7
Wear Pointwind farm8.2operational6.0
Cuckoo Grove Farmsolar farm6.1operational7.1
Rhoscrowther - Turbine Wind Farmwind farm12.9refused7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7491, -5.0407).