Energy Projects Near You

Dragon Long Meadow Solar farm (9.9 MW)

Dragon Long Meadow Solar farm is a 9.9 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 March 2023; the record was last updated on 17 January 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
operationalstatus in REPD
17 January 2022record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
22 December 2021Application submitted
14 January 2022Planning permission granted
13 March 2023Operational

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
operational
Record last updated
17 January 2022
Operator or applicant
Dragon LNG Limited / Anesco Limited
Planning authority
Pembrokeshire
Planning application reference
21/0986/PA
Site area
14.7 ha
Address (REPD)
Dragon LNG Meadow, The Land at West Perimeter Road, Milford Haven
Council area (by location)
Pembrokeshire
Time to decision
3 weeks
Name in REPD
Dragon Long Meadow - Solar farm
REPD reference
10415

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wear Pointwind farm8.2operational0.5
Dragon Energy Park Wind Farmwind farm14.4under construction1.4
Pembroke Power Station, Pwllcrochanbattery storage350approved, not built2.5
Rhoscrowther - Turbine Wind Farmwind farm12.9refused2.8
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built3.3
Liddeston Ridge Solar Park (Milford Haven)solar farm5operational3.3
Hoplass Farmsolar farm10operational3.8
Wogaston Solar Farmsolar farm5.3operational4.1
Goldborough Road, Hundletonbattery storage350approved, not built4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7033, -5.0031).