Goldborough Road, Hundleton (350 MW battery storage)

Goldborough Road, Hundleton is a 350 MW battery storage project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 January 2025, not yet built; the record was last updated on 18 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

350 MWbattery storage
approved, not builtstatus in REPD
18 November 2025record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
10 May 2024Application submitted
6 January 2025Planning permission granted
6 January 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
350 MW
Status (REPD)
approved, not built
Record last updated
18 November 2025
Operator or applicant
Pembroke Green Limited (Enso Energy and Cero Generation)
Planning authority
Pembrokeshire
Planning application reference
24/0133/PA
Address (REPD)
Goldborough Road, Hundleton
Council area (by location)
Pembrokeshire
Time to decision
34 weeks
Name in REPD
Goldborough Road, Hundleton - Battery Energy Storage
REPD reference
15277

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hoplass Farmsolar farm10operational0.7
Wogaston Solar Farmsolar farm5.3operational1.2
Corston Windfarmwind farm7.9refused1.3
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built1.6
Pembroke Power Station, Pwllcrochanbattery storage350approved, not built1.8
Rhoscrowther - Turbine Wind Farmwind farm12.9refused2.3
West Orielton Farmsolar farm5application withdrawn3.4
Wear Pointwind farm8.2operational4.0
Dragon Long Meadow Solar farmsolar farm9.9operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6663, -5.0035).