Energy Projects Near You

Wogaston Solar Farm (5.3 MW)

Wogaston Solar Farm is a 5.3 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
21 December 2012Application submitted
27 June 2013Refused by the planning authority
27 November 2013Appeal lodged
16 April 2014Planning permission granted
16 April 2014Appeal allowed
1 January 2015Construction started
17 March 2015Operational

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Elgin Energy EsCo
Planning authority
Pembrokeshire
Planning application reference
12/0906/PA
Appeal reference
APP/N6845/A/13/2203220
Address (REPD)
Land at Wogaston Farm
Council area (by location)
Pembrokeshire
Time to decision
69 weeks
REPD reference
5232

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hoplass Farmsolar farm10operational0.6
Goldborough Road, Hundletonbattery storage350approved, not built1.2
Rhoscrowther - Turbine Wind Farmwind farm12.9refused1.5
Corston Windfarmwind farm7.9refused2.3
Pembroke Power Station, Pwllcrochanbattery storage350approved, not built2.3
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built2.5
Dragon Long Meadow Solar farmsolar farm9.9operational4.1
Wear Pointwind farm8.2operational4.1
West Orielton Farmsolar farm5application withdrawn4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6685, -5.0209).