Energy Projects Near You

Renewable energy projects in Pembrokeshire

74 solar, wind or battery projects of 150 kW or more are located in Pembrokeshire (REPD, July 2026 extract): 9 pending, 21 approved but not running, 29 operational and 10 refused. The council refused 13 of 61 decided applications (21%; UK 19%), with a median 24 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

74projects in the council area
9awaiting a decision
21approved, not running
21%of decisions refused

How Pembrokeshire decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Projects in Pembrokeshire

Projects of 1 MW and more (49)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Pembroke Power Station, Pwllcrochanbattery storagebattery storage350approved, not builtupdated Dec 2025Sep 2024granted Jan 2025Dec 2025
Goldborough Road, Hundletonbattery storagebattery storage350approved, not builtupdated Nov 2025May 2024granted Jan 2025Nov 2025
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storagebattery storage49.9approved, not builtupdated Nov 2024Jan 2024granted Oct 2024Nov 2024
Fenton Home Farmsolar farmsolar farm31.3operationalupdated Nov 2014Jul 2013granted Dec 2013Nov 2014
Alleston Solar Farmsolar farmsolar farm30approved, not builtupdated May 2026Dec 2024granted Mar 2026May 2026
White House Farmsolar farmsolar farm30application submittedupdated Jan 2026Dec 2025—Jan 2026
Tiers Cross Solar Farmsolar farmsolar farm24operationalupdated Feb 2015May 2013granted Oct 2013Feb 2015
Dragon Energy Park Wind Farmwind farmwind farm14.4under constructionupdated Feb 2026Jul 2023granted Oct 2024Feb 2026
Rhoscrowther - Turbine Wind Farmwind farmwind farm12.9refusedupdated Feb 2022Oct 2021refused Oct 2022Feb 2022
Shoals Hook Farmsolar farmsolar farm12.1operationalupdated Jul 2017May 2014granted Oct 2014Jul 2017
White House Farmbattery storagebattery storage12application submittedupdated Jan 2026Dec 2025—Jan 2026
Rudbaxton Solar Parksolar farmsolar farm10.8operationalupdated May 2014Feb 2012granted Jul 2012May 2014
Hoplass Farmsolar farmsolar farm10operationalupdated Sep 2015Feb 2013granted Apr 2014Sep 2015
Blackberry Lane Solar Farmsolar farmsolar farm10approved, not builtupdated Feb 2026Mar 2024granted May 2025Feb 2026
Dragon Long Meadow Solar farmsolar farmsolar farm9.9operationalupdated Jan 2022Dec 2021granted Jan 2022Jan 2022
Jordanston Wind Farmwind farmwind farm9.8refusedupdated Jul 2001Sep 1997refused Sep 2001Jul 2001
West Farm, Cosheston Solar Farmsolar farmsolar farm9under constructionupdated Feb 2026Dec 2023granted Mar 2024Feb 2026
Trecoed Farmsolar farmsolar farm8.9permission expiredupdated Feb 2022Nov 2018granted Mar 2022Feb 2022
Wear Pointwind farmwind farm8.2operationalupdated May 2015Oct 2009granted May 2010May 2015
Chapel Hillsolar farmsolar farm8operationalupdated Jun 2015May 2014granted Jul 2014Jun 2015
Corston Windfarmwind farmwind farm7.9refusedupdated Apr 2005Oct 1995refused Mar 1996Apr 2005
Cilciffeth 'A' Wind Farmwind farmwind farm7.8refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005
Cilciffeth 'B' Wind Farmwind farmwind farm7.8refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005
West Farm (Solar)solar farmsolar farm7.7operationalupdated Sep 2015May 2012granted Nov 2012Sep 2015
Clawddcam-Mathry Solar Farmsolar farmsolar farm7.5abandonedupdated Feb 2019May 2012granted Dec 2013Feb 2019
Trenewydd Wind Farmwind farmwind farm6.3refusedupdated Apr 2005Feb 1999refused Oct 1999Apr 2005
Golden Hillsolar farmsolar farm6.2operationalupdated Jul 2017May 2014granted Sep 2014Jul 2017
Yerbeston Gate Farmsolar farmsolar farm6.1operationalupdated Feb 2016Sep 2013granted Dec 2013Feb 2016
Cuckoo Grove Farmsolar farmsolar farm6.1operationalupdated Sep 2018Nov 2012granted Apr 2013Sep 2018
Ambleston Solar Panelssolar farmsolar farm6operationalupdated Jan 2014Jun 2011granted Aug 2011Jan 2014
Crundale / Fenton Home Farm (extension)solar farmsolar farm5.9operationalupdated Apr 2015Sep 2014granted Nov 2014Apr 2015
Wogaston Solar Farmsolar farmsolar farm5.3operationalupdated May 2015Dec 2012granted Apr 2014May 2015
Jordanston Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Jun 2012granted Sep 2012Jun 2013
Liddeston Ridge Solar Park (Milford Haven)solar farmsolar farm5operationalupdated Sep 2015Oct 2012granted Jan 2013Sep 2015
North Tenementsolar farmsolar farm5operationalupdated Oct 2017Jul 2015granted May 2016Oct 2017
West Orielton Farmsolar farmsolar farm5application withdrawnupdated Jan 2016Aug 2015—Jan 2016
Popehill Farmsolar farmsolar farm5operationalupdated Aug 2017Oct 2015granted May 2016Aug 2017
Oak Cottagesolar farmsolar farm4.9operationalupdated Nov 2015Jan 2014granted Jun 2014Nov 2015
Langton Farm Solar parksolar farmsolar farm4.4operationalupdated Dec 2015Mar 2013granted Nov 2013Dec 2015
Bluestone National Park Resort, Canaston Wood Solar Farmsolar farmsolar farm4application submitted may be out of dateupdated Jan 2023Dec 2022—Jan 2023
Castle Pill - Repoweringwind farmwind farm3.2operationalupdated Nov 2013Jun 2005granted Dec 2005Nov 2013
Newhouse Farm, Canaston Bridgewind farmwind farm3application withdrawnupdated Nov 2025Jun 2025—Nov 2025
Land West of Roberts Wall Farsolar farmsolar farm2.5operationalupdated Mar 2016Feb 2015granted Jun 2015Mar 2016
Rhoscrowther Wind Clusterwind farmwind farm2.2refusedupdated Oct 2001Nov 1999refused Apr 2001Oct 2001
Princes Gate Spring Waterwind farmwind farm1.6operationalupdated Jan 2015Nov 2011granted Jul 2013Jan 2015
Lawrence Landfillwind farmwind farm1.6operationalupdated May 2017Apr 2013granted Aug 2014May 2017
Rhosygilwen Solar Farmsolar farmsolar farm1operationalupdated Aug 2011Nov 2010granted Jan 2011Aug 2011
Lodge Farm 1wind turbinewind turbine1operationalupdated Mar 2010Jan 2005granted Oct 2005Mar 2010
MELIN, Pen Y Bankwind farmwind farm1refusedupdated Dec 2013Feb 2013refused Oct 2013Dec 2013
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Rhos-Hill, Cilgerranwind turbinewind turbine0.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023
Bolton Hill WTWsolar farmsolar farm0.5operationalupdated Jul 2020Jul 2018granted Oct 2018Jul 2020
Tesco Superstore, London Roadrooftop solarrooftop solar0.5application submittedJun 2026——
Summerton Farm, Sagestonwind turbinewind turbine0.3refusedupdated Jul 2024Nov 2023refused Mar 2024Jul 2024
Heatherton World Of Activity, Heatherton Sports Park Solar Arrayssolar farmsolar farm0.2approved, not builtupdated Apr 2023Dec 2022granted Mar 2023Apr 2023
Kiln Park Holiday Centre, Marsh Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023
Tennis Courts, St Brides Castlerooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Oct 2025granted Apr 2026Jun 2026
Trebover Farmwind turbinewind turbine0.2approved, not builtupdated Jun 2025Nov 2024granted May 2025Jun 2025
Pensygwarne, Croesgochwind turbinewind turbine0.2approved, not built may be out of dateupdated Mar 2022Dec 2021granted Sep 2022Mar 2022
Consort Equipment Products - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2024Mar 2024granted May 2024Jun 2024
Honeyborough Industrial Estate - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Castle Terrace, Pill Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2026Jul 2025granted Feb 2026Mar 2026
Fishguard Leisure Centre Car Park - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jan 2026Jul 2025refused Dec 2025Jan 2026
Steynton Road And Sheffield Drive - Micro Energy Battery Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Jul 2025granted May 2026Jun 2026
Bridge Innovation Centre, Pembrokeshire Science - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
Castle Quarry - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025
Station Road, Brunel Quay - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025
Meyrick Street - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025
St Daniels Hill - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedupdated Oct 2025Sep 2025—Oct 2025
Waterloo Industrial Estate, Eastern Avenue - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026
Withybush Road, Fishguard Road - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——
Withybush Road, Withybush Industrial Estate - Micro Energy Storage Systembattery storagebattery storage0.2application submittedMay 2026——
Bro Preseli Solar Panels & Battery Storagerooftop solarrooftop solar—application withdrawnupdated Oct 2024Jun 2023—Oct 2024
Puffin Producerooftop solarrooftop solar—operationalupdated Aug 2024——Aug 2024
Summerton Farm, Sagestonwind turbinewind turbine—application submittedupdated Jun 2025May 2025—Jun 2025

Postcode districts in Pembrokeshire

DistrictProjects within 10 kmPendingApprovedOperational
SA3513233
SA367222
SA378222
SA413101
SA425010
SA61224513
SA6213209
SA6312207
SA649011
SA659011
SA662002
SA676104
SA6812244
SA698124
SA708133
SA713431610
SA724051614
SA733841515

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Pembrokeshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.