Golden Hill (6.2 MW solar farm)

Golden Hill is a 6.2 MW solar farm project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 3 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
3 July 2017record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
7 May 2014Application submitted
10 September 2014Planning permission granted
1 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
3 July 2017
Operator or applicant
John Laing Environmental Assets Group
Planning authority
Pembrokeshire
Planning application reference
14/0129/PA
Site area
16.1 ha
Address (REPD)
Land East of Mylett's Hill, Golden Hill, Pembroke, Pembrokeshire
Council area (by location)
Pembrokeshire
Time to decision
18 weeks
REPD reference
2325

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Farm, Cosheston Solar Farmsolar farm9under construction1.5
West Farm (Solar)solar farm7.7operational1.6
Alleston Solar Farmsolar farm30approved, not built2.1
Blackberry Lane Solar Farmsolar farm10approved, not built3.5
West Orielton Farmsolar farm5application withdrawn4.7
Chapel Hillsolar farm8operational5.5
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built5.5
Pembroke Power Station, Pwllcrochanbattery storage350approved, not built6.0
Dragon Energy Park Wind Farmwind farm14.4under construction6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6849, -4.9078).