Pembroke Power Station, Pwllcrochan (350 MW battery storage)

Pembroke Power Station, Pwllcrochan is a 350 MW battery storage project in Pembrokeshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 31 January 2025, not yet built; the record was last updated on 2 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

350 MWbattery storage
approved, not builtstatus in REPD
2 December 2025record last updated
Pembrokeshirecouncil area

Planning timeline

DateStage
17 September 2024Application submitted
31 January 2025Planning permission granted
31 January 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
350 MW
Status (REPD)
approved, not built
Record last updated
2 December 2025
Operator or applicant
RWE Generation UK Plc
Planning authority
Pembrokeshire
Planning application reference
24/0600/PA
Address (REPD)
Pembroke Power Station, Pwllcrochan
Council area (by location)
Pembrokeshire
Time to decision
19 weeks
Name in REPD
Pembroke Power Station, Pwllcrochan - Battery Storage
REPD reference
14913

Who decides

ApplicationsPembrokeshireUK
Decided applications (solar, wind, battery)6110,236
Refused13 (21%)19%
Solar refused1 of 3112%
Onshore wind refused11 of 1645%
Battery storage refused1 of 1416%
Median time from submission to decision23.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Greenlink Converter Station - Lambeeth Battery Energy Storagebattery storage49.9approved, not built0.9
Hoplass Farmsolar farm10operational1.8
Goldborough Road, Hundletonbattery storage350approved, not built1.8
Rhoscrowther - Turbine Wind Farmwind farm12.9refused2.1
Wear Pointwind farm8.2operational2.3
Wogaston Solar Farmsolar farm5.3operational2.3
Dragon Long Meadow Solar farmsolar farm9.9operational2.5
Corston Windfarmwind farm7.9refused2.9
Dragon Energy Park Wind Farmwind farm14.4under construction3.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6818, -4.9949).